Day 105
The steady light rain all day has been perfect for the new seed. Temps in upper 50's is also right on I think.
Inside they got the wall going down the stairs dressed up.
And the door at the bottom of the stairs is in
There's a wet spot in the middle of the basement floor. Will need to figure out what's up with that!
The correct walkout basement doors finally got installed
Tile work continued. They started on the Tuscan Blue today. They asked me if I wanted to alternate the English Grey with the Tuscan Blue where they meet to kind of "weave" the colors together. The alternative of course would be to rip the tiles at the split. What would you do?
They fixed the areas with bubbles under the underlayment
And they finally got the built-in rack trimmed correctly. The painters will need to patch that hole from the outlet that was put on the wrong side initially.
The steady light rain all day has been perfect for the new seed. Temps in upper 50's is also right on I think.
Inside they got the wall going down the stairs dressed up.
And the door at the bottom of the stairs is in
There's a wet spot in the middle of the basement floor. Will need to figure out what's up with that!
The correct walkout basement doors finally got installed
Tile work continued. They started on the Tuscan Blue today. They asked me if I wanted to alternate the English Grey with the Tuscan Blue where they meet to kind of "weave" the colors together. The alternative of course would be to rip the tiles at the split. What would you do?
They fixed the areas with bubbles under the underlayment
And they finally got the built-in rack trimmed correctly. The painters will need to patch that hole from the outlet that was put on the wrong side initially.