My approach would probably not dig it out and create a reservoir for water under the slab with gravel for water to accumulate. Just level it off pour a 4" slab the is reinforced with a 24" grid of 1/2" rebar.
While I mostly agree that we don't know the moisture content to give a better piece of advice, leveling off a piece of earth renders it uncompacted which is horrible for concrete because it puts it under stress when an air pocket occurs.
In the case that water is an issue it would be better to add a drain to my design, which isn't really needed because 0-1/2inch gravel when compacted is practically impervious to water.
Essentially anything bigger than 1/2-3/4inch Gravel becomes a substrate that allows water to flow through it or create a "bassin". While anything smaller acts like concrete..
The issue with building on existing terrain is that you don't know what is underneath it, and the bearing load of the soil which may change from location to location. Hence my recommendation to create a uniform platform which would have a "known" load bearing soil.
As far as thickness goes, 4 inches is usually sufficient for a patio but at the price of an extra half meter cube of concrete, for this project, I would pour off some extra concrete just for long term longevity. (An 8 by 12 platform at 4inches thick or 5 average would require 1cu. Meter of concrete while 6 inches on center with the sides thicker would require 1.5cu. Meter.
Lastly, I'm unsure whether OP plans on mixing concrete bags or getting a ready-mix truck to deliver the concrete; but I would recommend getting a truck on concrete since it will be a more even batch, which you could order in something like 27MPa. If the area is subjected to below freezing temperatures, then request 4% of entrained air. Which is essentially tiny microbubbles that allow for water to expand when it is freezing, this would prevent surface cracking.
It also makes more sense to order 2cu. Meter than 1.1-1.3cu.m when ordering a truck ...
(1cu.m is 1.3 cu.yards
2cu.m is around 2.6cu.yards of concrete, meaning if they pour 4inches they would need around 1.5cu.y ordered)
Hope this helps...