Neuropel
Member
I want to construct a 74'x40' pole barn/workshop in Western PA, about an hour north of Pittsburgh. I live
near the Amish, and I have checked out many of their barns in the area
which are beautiful hemlock sided buildings with gambrel roofs. One of
these buildings will perfectly suit my needs, and I have now found an
Amish builder willing to construct the barn. I also have ordered the
green hemlock lumber from a nearby Amish lumber yard that produces
beautiful 1"x12" hemlock board and batten siding. The barn/workshop I'm building will have a complete second floor for hay storage (thanks to the gambrel roof design). First floor height will be 10'. The building will have 4 rows of posts (the perimeter row plus two inner rows for attaching stall walls and floor joists for the second floor). My current plans call
for 50 or so 6"x6" posts that will need to be set. The typical
construction has posts set into the ground, which bothers me somewhat especially given the new methods used in pressure treated lumber. I've seen things like permacolumn and
post protector that look promising but pricey (Permacolumns run between $75-$80 each, plus the shipping will be expensive since they weigh about 120# each. Post Protectors are $40 each, plus the cost of the treated posts which will add an additional $40 per post. I've also read and seen plans where concrete piles are
poured in the ground, and the posts are then set into a metal bracket
"foot" bolted onto the pile. This seems ideal for my situation but I have several questions. I have a tractor with a post hole digger, and was planning to purchase a 12" auger to dig the holes, and I suspect I could go down nearly 4 feet.
I was reading another thread here and saw the mention of "Hilti Bolts", which seem like an ideal solution for me since I could drill and pour the piers ahead of time and then drill the holes and set the bolts and hardware for each post as needed. It's unrealistic to think I would be able to accurately set all the hardware in wet piers, hence my dilema. The spans for my posts vary, but the maximum is around 10'.
Would I be ok to just put some rebar in the holes and pour the piers, and use the hilti bolt solution?
Also, I'd like to pour the floor for the workshop portion and the middle aisle of the barn after the building is erected (mainly due to the cruddy weather we have in Western PA. Are there any glaring problems with my plan?
Sorry about the message length...I just want to plan this so that I
don't have to rebuild my barn in 30 years. I figure a little planning
now might be worth a lot later.
Thanks
T. Kirby
Spring Church, PA
near the Amish, and I have checked out many of their barns in the area
which are beautiful hemlock sided buildings with gambrel roofs. One of
these buildings will perfectly suit my needs, and I have now found an
Amish builder willing to construct the barn. I also have ordered the
green hemlock lumber from a nearby Amish lumber yard that produces
beautiful 1"x12" hemlock board and batten siding. The barn/workshop I'm building will have a complete second floor for hay storage (thanks to the gambrel roof design). First floor height will be 10'. The building will have 4 rows of posts (the perimeter row plus two inner rows for attaching stall walls and floor joists for the second floor). My current plans call
for 50 or so 6"x6" posts that will need to be set. The typical
construction has posts set into the ground, which bothers me somewhat especially given the new methods used in pressure treated lumber. I've seen things like permacolumn and
post protector that look promising but pricey (Permacolumns run between $75-$80 each, plus the shipping will be expensive since they weigh about 120# each. Post Protectors are $40 each, plus the cost of the treated posts which will add an additional $40 per post. I've also read and seen plans where concrete piles are
poured in the ground, and the posts are then set into a metal bracket
"foot" bolted onto the pile. This seems ideal for my situation but I have several questions. I have a tractor with a post hole digger, and was planning to purchase a 12" auger to dig the holes, and I suspect I could go down nearly 4 feet.
I was reading another thread here and saw the mention of "Hilti Bolts", which seem like an ideal solution for me since I could drill and pour the piers ahead of time and then drill the holes and set the bolts and hardware for each post as needed. It's unrealistic to think I would be able to accurately set all the hardware in wet piers, hence my dilema. The spans for my posts vary, but the maximum is around 10'.
Would I be ok to just put some rebar in the holes and pour the piers, and use the hilti bolt solution?
Also, I'd like to pour the floor for the workshop portion and the middle aisle of the barn after the building is erected (mainly due to the cruddy weather we have in Western PA. Are there any glaring problems with my plan?
Sorry about the message length...I just want to plan this so that I
don't have to rebuild my barn in 30 years. I figure a little planning
now might be worth a lot later.
Thanks
T. Kirby
Spring Church, PA