Kubota-Orange8998
New member
- Joined
- Apr 19, 2022
- Messages
- 1
- Tractor
- Kubota BX1880
I hired a deadbeat contractor and now I need to know what is the best way to fix this mistake.
To summarize a long story, I hired a contractor to excavate and complete foundation work (42" deep x 12" wide concrete footings then a 4" thick concrete floor) so that a metal tube storage building could be installed. The contractor did 75% of the excavation and then never returned to finish the job or do any concrete work. After months of broken promises, I am left with a hole in the ground. Roughly 4ft wide x 4 ft deep in the shape of a rectangle.
I want the building in the location that was partially excavated, so I need to fill the open excavation areas so I can "start over" with the same location.
At first, I was thinking of finding fill dirt with high clay content and fill the holes open trenches in. Then rent a ride on roller to compact it. But then a friend of mine suggested filling in the open trenches with stone and then add dirt on top of it.
I had an eager, young excavation professional on site to evaluate. He would not take on the job because he has never done something like this before. He said settling will be a major concern.
My question to you all is: What is the "proper" way to fill in the hole and then prep the area for a metal tube storage building could be installed. I will not have any concrete this time around. The building will be installed on compacted dirt and stone and secure by mobile home anchors. The building is basically a carport with the sides and ends closed up and roll up doors to move equipment in and out.
To summarize a long story, I hired a contractor to excavate and complete foundation work (42" deep x 12" wide concrete footings then a 4" thick concrete floor) so that a metal tube storage building could be installed. The contractor did 75% of the excavation and then never returned to finish the job or do any concrete work. After months of broken promises, I am left with a hole in the ground. Roughly 4ft wide x 4 ft deep in the shape of a rectangle.
I want the building in the location that was partially excavated, so I need to fill the open excavation areas so I can "start over" with the same location.
At first, I was thinking of finding fill dirt with high clay content and fill the holes open trenches in. Then rent a ride on roller to compact it. But then a friend of mine suggested filling in the open trenches with stone and then add dirt on top of it.
I had an eager, young excavation professional on site to evaluate. He would not take on the job because he has never done something like this before. He said settling will be a major concern.
My question to you all is: What is the "proper" way to fill in the hole and then prep the area for a metal tube storage building could be installed. I will not have any concrete this time around. The building will be installed on compacted dirt and stone and secure by mobile home anchors. The building is basically a carport with the sides and ends closed up and roll up doors to move equipment in and out.