I'm brant and I'm new to this forum.
I'm doing a little mining and before I get started I have some questions about the material that we will be cutting.
The top layers are red clay mixed with gravel and as you get to the lower layer it becomes progressively harder and more cemented.
Here is a pic of the strata.
strata strip2354.jpg - File Shared from Box - Free Online File Storage
In the literature the say that a D6 can push about 200YPH over 130 ft or so.
We need to push at least 100YPH.
What does that go down to if you are getting into harder material??
I'm doing a little mining and before I get started I have some questions about the material that we will be cutting.
The top layers are red clay mixed with gravel and as you get to the lower layer it becomes progressively harder and more cemented.
Here is a pic of the strata.
strata strip2354.jpg - File Shared from Box - Free Online File Storage
In the literature the say that a D6 can push about 200YPH over 130 ft or so.
We need to push at least 100YPH.
What does that go down to if you are getting into harder material??