MechE1
Silver Member
- Joined
- Sep 4, 2013
- Messages
- 196
- Location
- Urbana, Il
- Tractor
- Ingersoll 448 with 42" tiller and 60" deck. John Deere 3046R, cab, T&T, H165 loader with 4and1, 60D Autoconnect, 72" boxblade, 59" snowblower
I will be needing more storage in the near future. At first I was leaning toward a pole barn, but with the discussion and what I've learned reading on this outstanding board, I will be building a stick framed building instead. Size will be about 24ft x 32ft initially.
Short term, the building will be used for equipment/vehicle storage. Longer term (within 5 yrs), the building will be expanded and will also become a wood shop (future new addition to the non-existent garage) moved from the houses basement (man I get tired of carrying those 3/4" sheets down the stairs), and also a metal shop. I have a spare boiler that would be ideal for radiant heating. The issue is up front cost. With everything else that I will have going on, I cannot see financing a concrete floor at this time, with all that is required for radiant heat, but the storage area is required now.
The question, and I've seen it done a lot, will the contractor charge more for pouring a floor in a building that already has the walls up? If so, what´s a good percentage estimate over not having the walls up? Would it cost the same? I plan on doing all the labor except the pour. I would put a standard footing and block foundation. Then rock but leave room for the foam/concrete. I realize the issues around the overhead door(s)/floor seal, but that can be a addressed one way or another with no real issues until the floor is in.
Short term, the building will be used for equipment/vehicle storage. Longer term (within 5 yrs), the building will be expanded and will also become a wood shop (future new addition to the non-existent garage) moved from the houses basement (man I get tired of carrying those 3/4" sheets down the stairs), and also a metal shop. I have a spare boiler that would be ideal for radiant heating. The issue is up front cost. With everything else that I will have going on, I cannot see financing a concrete floor at this time, with all that is required for radiant heat, but the storage area is required now.
The question, and I've seen it done a lot, will the contractor charge more for pouring a floor in a building that already has the walls up? If so, what´s a good percentage estimate over not having the walls up? Would it cost the same? I plan on doing all the labor except the pour. I would put a standard footing and block foundation. Then rock but leave room for the foam/concrete. I realize the issues around the overhead door(s)/floor seal, but that can be a addressed one way or another with no real issues until the floor is in.