powerstroke444e
Veteran Member
I got several bids for a new geo system and all were north of $20,000
So I did some digin and found a dealer that was setting on some units that he would like to move. Here is my problem or questions.
I am putting a 6 ton unit in and putting 600 foot of pipe per ton. Should be complete material cost of under $8K unlesse I have to do it twice. The contractors that bid it were going to put in less pipe and then in and out pipe were going to be in the same trench. When I said what happens if you keep them seperate trenches they said that would cost to much??wtf
So I have bored them for others but I don't have a bore machine anymore. So how deep do I need the lines??? I have a 60" trencher which would be the easiest but don't know if its deep enought to get it to work well. If needed I could get something that will trench 72" or I could dig it all but the thought of that much time on a hoe don't sound fun.
Although anything is better than 2000 gal of propane.
Attached is photo of loop system.
So I did some digin and found a dealer that was setting on some units that he would like to move. Here is my problem or questions.
I am putting a 6 ton unit in and putting 600 foot of pipe per ton. Should be complete material cost of under $8K unlesse I have to do it twice. The contractors that bid it were going to put in less pipe and then in and out pipe were going to be in the same trench. When I said what happens if you keep them seperate trenches they said that would cost to much??wtf
So I have bored them for others but I don't have a bore machine anymore. So how deep do I need the lines??? I have a 60" trencher which would be the easiest but don't know if its deep enought to get it to work well. If needed I could get something that will trench 72" or I could dig it all but the thought of that much time on a hoe don't sound fun.
Although anything is better than 2000 gal of propane.
Attached is photo of loop system.