Running sch40 electrical in floor before concrete?

   / Running sch40 electrical in floor before concrete? #11  
I always lay out my wire and then slide my conduit over it. 3/4 is too small for most things, I would go one inch.

If you want a really smooth conduit line, use one inch, white PEX. I've never used it under a slab for wire, but I use it all the time for getting wire down an exterior wall full of insulation.
 
   / Running sch40 electrical in floor before concrete? #12  
Run the pair of conduit sweeps up to the box location. Either install the box and cover with tape before the pour. Bore couple of holes in scrap wood to match the box hole pattern. Slide those on the sweeps to hold the spacing during the pour.

Don't want a tee embedded in the slab. When feeding the wire though there is no way to control which port it will exit out of. Any pipe in the slab should only have one in and one out.
 

Tractor & Equipment Auctions

CAT D6C Crawler Dozer (A47477)
CAT D6C Crawler...
(2) DOUBLE AXLE FENDERS (A54756)
(2) DOUBLE AXLE...
2000 JOHN DEERE 310SE BACKHOE (A52705)
2000 JOHN DEERE...
2008 UTILITY DRY VAN TRAILER 53X102 (A54607)
2008 UTILITY DRY...
1827 (A51248)
1827 (A51248)
2015 Hitachi PC138 (A47477)
2015 Hitachi PC138...
 
Top