Forst starts on top of the ground and moves down and across.
That iron lid is going to freeze first.
You make yourself a rubber gasket that fits the mating surfaces between lid and frame first. Then you trench about 2 feet down a couple feet back from the riser and drop 2" foam in the trench for a frost fence.
Put about 4" foam board over the iron lid and you should be home free.