Problem with concrete floor in a quonset shop bulding 24/30

   / Problem with concrete floor in a quonset shop bulding 24/30 #1  

travlitt

Platinum Member
Joined
Jun 12, 2012
Messages
680
Location
Texas
Tractor
8050C Branson, Branson 2400, 8N Ford, Round Fender John Deere 110, 3 60" ZTR mowers, a bunch of ride on mowers, 8' Brush hog , 15' Bat wing
I recently purchased a 10 acres with a home and a Quonset building.This land joins my land.
In the distant past a previous owner buried a shipping container and used it as a storm shelter.
The next owner poured a concrete slab and built a 24x30 Quonset shop building over it.

Problem and how to fix it.

The back 1/2 of the floor is sunk in about 1'. Container rusted and caved in.
I was aware of this condition before I bought it, but thought it could be fixed.

Pics of what I have done so for.
Jack hammered the entire floor.
023.JPG
Notice cavity under the floor.
036.JPG
Destroyed what was left of the container top and pushed all of the busted up concrete into the hole.
010.JPG
Lifted the front of the shop and blocked it up.
037.JPG
Almost ready to pour concrete.
017.JPG

The pad and building will be moved forward about 10' to be on solid ground.
I will pour to day if all goes as planned
Sure has been a fun project
 
Last edited:
   / Problem with concrete floor in a quonset shop bulding 24/30 #2  
Man, you took on that project! doing it right too IMO, great way to tackle that, impressive.
 
   / Problem with concrete floor in a quonset shop bulding 24/30 #3  
Good job, that is one heck of a project.
 
   / Problem with concrete floor in a quonset shop bulding 24/30 #4  
No chairs under the re-bar?
 
   / Problem with concrete floor in a quonset shop bulding 24/30 #5  
Did you find Jimmy Hoffa under there?
 
   / Problem with concrete floor in a quonset shop bulding 24/30 #6  
I agree on putting something under the rebar to keep it where you want it. Concrete will take it down without support.
 
   / Problem with concrete floor in a quonset shop bulding 24/30
  • Thread Starter
#7  
I put the chairs under the rebar just ahead of the pour.
We poured today..12 yards.
There is a thunder storm brewing now..sure hope it has dried enough to survive it with no damage.
We have it tied down because of the wind.
 
   / Problem with concrete floor in a quonset shop bulding 24/30 #8  
It must be REALLY windy in Texas if you have to tie down your concrete slabs.

:)

Bruce
 
   / Problem with concrete floor in a quonset shop bulding 24/30 #9  
It must be REALLY windy in Texas if you have to tie down your concrete slabs. :) Bruce
hahaha this made me laugh:)
 
   / Problem with concrete floor in a quonset shop bulding 24/30
  • Thread Starter
#10  
The building is what is tied down. As you can see it is up on blocks.
 

Tractor & Equipment Auctions

2014 Ford F-350 Omaha Crane Service Truck (A48081)
2014 Ford F-350...
UNUSED 7/10 in. Twisted Manila Rope (A50860)
UNUSED 7/10 in...
John Deere Gator XUV835M 4X4 Utility Cart (A48082)
John Deere Gator...
Diesel Fuel Tank with Pump (A50860)
Diesel Fuel Tank...
CATERPILLAR 308E2 CR EXCAVATOR (A50458)
CATERPILLAR 308E2...
(2) Heavy Duty Tow Straps (A50860)
(2) Heavy Duty Tow...
 
Top