creekbend
Super Star Member
The other members have been helpful. I only wish to add that Gravel prices are very high in our area. Best wishes. BTW, I also agree that 16 foot wide is too much.
Where in Wisconsin? It's a big state and the terrain/local materials vary a lot (i.e in west central Wisconsin our "base course" was granite breaker rock). Southern Wis uses mostly limestone. Figure +/- $100 hour for Bobcat work to level it. Material itself depends but plan on letting it settle for a year or two and then re-top it. You can probably figure about $100+ per load on a 14 yard dump truck but that's just a guess since I don't have my last bill handy.
620 ft??? That's a lot! You sure you need all that? If you aren't going to access the back of the property on a regular basis then you might want to do it in stages. And whatever you do, get any electrical/water/whatever to the other side.
The other members have been helpful. I only wish to add that Gravel prices are very high in our area. Best wishes. BTW, I also agree that 16 foot wide is too much.
I'm in South Central Wisconsin.
The 620 feet includes 60 feet behind my pole building. That said, the other 560 feet gets me to the edge of my woods which is about halfway back. The house lot is located from the edge of the woods to 200 feet in so we'll need a little more after this.
Great point on getting electrical to the other side. I'll ask Alliant about that on Monday. Thanks.