I'd appreciate expanding these tips to include gravel drives, as I am about to have to redo my 1600' drive as my home is nearing completion and after the concrete, lumber and brick packages were delivered, it is a mess.
I hired someone with a dozer to cut it in and had a base of #2 and #3 limestone gravel put in before construction began. Now I need to grade it again as it is humped up in the middle something awful, and put a layer of dense grade limestone (with or without the dust?) on top.
Anyone know the best way to grade and pack this using a CUT, or should it be hired out again (ouch!)?