Yes, another electrical question. Oh, and propane too.

   / Yes, another electrical question. Oh, and propane too.
  • Thread Starter
#31  
My LP company isn't going to be much help. Just called them back and they want $3.50/ft for copper and $2.80/ft for plastic, plus fittings.
 
   / Yes, another electrical question. Oh, and propane too. #32  
My propane company didnt even charge me for pipe as long as i dug a 24” deep trench 300 feet to my shop. I only had to pay for regulator. They figured id use enough gas over the years heating my shop.
 
   / Yes, another electrical question. Oh, and propane too. #33  
When we built here in the Rocky Mountains 15 years ago there was a choice of either above ground or underground for about a 600 foot run. 200 amp service. We chose to put in two poles to cut the distance in half - these were less expensive than I had expected. From the last pole the lines dropped down to a transformer on the ground where they went underground the last 300 feet. The meter was on the transformer. Trenching was easy, the heavy underground wire was in large diameter heavy wall PVC tube. Cost was about $30K for all versus somewhere less than half that if we had stayed above ground the whole way. The utility did it all the work including inspections. We were happy not to have to look at wires coming across our land.

Seven years ago a flood wiped out the underground system. Floodwater swept the transformer and one of the poles away, pulling the whole underground system out of the ground. What a mess. We replaced the underground feed with a standard above ground feed and drop to the house. Cost of putting in new electrical was right at $5K.


WE WOULD NEVER GO UNDERGROUND AGAIN FOR TWO REASONS:

1. The transformer noise. With the underground system, the transformer on the ground made a constant hum. The noise wasn't loud enough that a person could hear it in town, but here in the quiet piney mountains, but we could alwyas hear it. It made a constant droning hum even though 300 feet away on a hillside. The utility said all the transformers make some noise, but in most locations there is enough background noise from wind, or traffic, or neighbors to drown out the transformer noise. Not so for us.
Believe me, if you value quiet you do NOT want that transformer close to your house.

2. The increased monthly cost. We were surprised at how high our undergound utility bills were. Not outrageous, and the same cost per kW/hr..... but still about 50% higher than we had expected. Comparing with neighbors, we seemed to be paying up to double what others were paying for similar houses. Being careful about electrical use didn't make a noticible difference. After the flood we elected to put the replacement lines overhead, not underground. Now the meter is at the house instead of at the transformer. Our monthly bill immediately dropped by 50%.

Some conclusions: In-ground electrical is expensive initially and ongoing. It can be noisy. It is more vulnerable to damage and difficult to repair. Repairs are on your dime. So is clean up. Your monthly costs may go up, but you won't know and cannot fight it because there is no way to compare.

rScotty

UG and OH are the same cost, per KWH, to the customer/member. The difference in your scenario is how it was metered. If it was metered at the trans, it was CT metered and normally that would be at a commercial rate.
 
Last edited:
   / Yes, another electrical question. Oh, and propane too. #34  
UG and OH are the same cost to the customer/member. The difference in your scenario is how it was metered. If it was metered at the trans, it was CT metered and normally that would be at a commercial rate.
Not necessarily. Here in idaho overhead is alot cheaper than underground. I have quite a few residential customers metered with ct’s and they still have residential rates. It depends upon utility.
 
   / Yes, another electrical question. Oh, and propane too. #35  
Not necessarily. Here in idaho overhead is alot cheaper than underground. I have quite a few residential customers metered with ct’s and they still have residential rates. It depends upon utility.

For initial install or per KWH? I've never seen KWH change depending on service type.
I did mistype and forgot to put, per KWH, in my post
 
   / Yes, another electrical question. Oh, and propane too. #36  
For initial install or per KWH? I've never seen KWH change depending on service type.
I did mistype and forgot to put, per KWH, in my post
Oh. I misunderstood your meaning of the same. Yes, cost per kwh is same.
 
   / Yes, another electrical question. Oh, and propane too. #37  
Oh. I misunderstood your meaning of the same. Yes, cost per kwh is same.

I thought it, just didn't type it. Yes, install cost are a lot higher for UG and it changes from utility to utility about how much they will charge for each.
I like the transformer as close as possible for voltage drop issues. Just because you did all the homework and paid extra for wire or equipment(up size, copper) does NOT mean the utility will do the same. They are going to undersize with the thought that no one will pull their full load at any given time. My house met code but I was having dimming/flickering issues, I had utility upgrade trans and wire and all my issues went away. My in-laws didn't listen to my suggestion and did as the OP suggest, secondary only from pole. The difference is, their service is 315+/-. They have not had any issues but they have a smaller house and they don't do any extra things(i.e. weld, extra lighting, etc...).
 
   / Yes, another electrical question. Oh, and propane too. #38  
In my area you can have 2 meters on the same lot before having to pay to have the line run.

I just added a 400a 3phase service to my shop, about 250' UG, transformer placed approx 20' from the shop.

I chose to run the conduit for the UG line myself so the only cost I incurred was the conduit (6in so not cheap) and a precast pad for the transformer. The utility company did everything else.
If I had chosen to do the OH line my cost would have been nothing, however I didn't want OH lines run through the woods across my driveway.

This was a new service, if I needed to upgrade an existing service it would have cost me.
 
   / Yes, another electrical question. Oh, and propane too. #39  
That's freakin' insane. $2.66' insane.

And I need 90-100' with no breaks/splices/couplings.

I don't think it's insane, just higher priced than it used to be. So what? If it was bad quality that would be different, but for my last project I inspected the coils before buying and at least it looks to be just like the old stuff - being soft copper easily bent. The color seems right for pure copper.

Anyway, I just put in 100 feet of of copper propane line - actually several lines radiating from a hub and each one continuous to its own low pressure regulator. I think I paid around 2.10/ft. for the copper tubing. The only problem was a couple of the made-in-China brass compression fittings which split when tightened.
I was able to find some old USA made ones to replace them.

And I sleep good because the pure copper line is durable. It will last far longer than I'll remember the price.

rScotty
 
   / Yes, another electrical question. Oh, and propane too. #40  
And I sleep good because the pure copper line is durable. It will last far longer than I'll remember the price.
Copper is durable and can be done by the homeowner, but it also depends on the soil and what it comes in contact with. Iron soils and concrete will corrode the copper. The poly pipe is non-corrodable but you need the special fittings and installation equipment which means a professional installation requirement.
 

Tractor & Equipment Auctions

2022 Spartan RZ-Pro Zero Turn Mower (A50860)
2022 Spartan...
Misc. Electronics (A50860)
Misc. Electronics...
2014 John Deere 8360R MFWD Tractor (A50657)
2014 John Deere...
Bad Boy Outlaw XP61 Zero Turn Mower (A48082)
Bad Boy Outlaw...
2008 Ford F-250 Knapheide Service Truck (A50323)
2008 Ford F-250...
2018 JLG 3246ES 32ft Electric Scissor Lift (A50322)
2018 JLG 3246ES...
 
Top