Total ditch length approximately 1/2 mile.
Figured on working both sides, total of one mile, with small machine to minimize ground compaction

Just bid a good mile or more of ditching, double it if you count both sides
This is the info we were going off of.

If the ditch is only 2640' total length.....15' wide, and 3' deep that is only a total of 2200yds of material......IF there werent already existing ditches.

So I'd say based on pics....that you are looking at excavating an approximate 1000yds of material total. This sounds way more plausible with a mini and a tractor with high capacity bucket.

With a ditching bucket a mini should be good for 25-30 yards per hour of material removal. So a good 40hr week give or take a bit.

From experience....using a mini to load a trailer, loader bucket, or anything other than just dumping in a pile is gonna slow you down big time. Gotta be slow, deliberate, and precise with your movements to not be banging into other equipment.

If the tractor can haul 2yds at a time and you can get 5 trips an hour.......thats 3 weeks of tractoring to build the berm. Still alot of seat time, but more doable without living on site for the next 3 months only shuttling dirt.

Get the mini in and out in a week. The tractor will quickly fall behind. But get the mini done and cut loose then use tractor for however long needed to shuttle the dirt.
 
   / Ditching job #92  
I think the math is a little off, and certainly not reflective of the pictures.

I read it as a mile, give or take, of total ditch. He said double if you count both sides.

Maybe I am wrong.....But I took that to only mean a mile total. And with a small 3 ton machine with limited reach.....he was figuring on doing one side.....from bottom of ditch up to grade (half the 15' width of the ditch) then coming down the other side. So either 1 mile of 15' wide ditch.....or two miles of 1/2 a ditch width.

So that said.....ditch is like a triangle.....15' x 3'. and 5280' long. So Im only coming up with 4400yds of material.

BUT.......the ditches are already there. This isnt a new ditch cut into flat ground....rather its reshaping of existing ditches. So alot of the material is already moved. Without measuring it....Id venture a guess that half the material is already removed.

So I think that puts it ~2200 or so yards still needing moved. Still alot for sure.

And I agree that transporting material 1/2 mile is gonna be the slow down. Keep the mini moving....pile dirt.....the tractor is more than capable of loading a full scoop from piles and doesnt need to be spoon-fed by the mini operator.

I have no answers for moving the dirt faster given the conditions. Maybe get the ditches mucked out then wait on dry conditions to load and use dump trucks?

Yeah, I realized I read the assignment wrong and was adding undue confusion and difficulty. Sometimes I get a little too excited as a keyboard warrior... It's easy to say how I would do it but I don't have any skin in the game.
 
   / Ditching job
  • Thread Starter
#93  
Yeah, I realized I read the assignment wrong and was adding undue confusion and difficulty. Sometimes I get a little too excited as a keyboard warrior... It's easy to say how I would do it but I don't have any skin in the game.

It’s understandable
These are smaller ditches on private, very delicate historic ground.
Gotta tread lightly. Owner is a continuous customer and I farm their property.
There’s a time & place for the big axe and a time & place for a scalpel. ;)
 
   / Ditching job #94  
A scalpel requires a lot more money to avoid all the good tissue around the wound.

Is the owner prepared to pay for scalpel type work?
 
   / Ditching job #95  
Smaller equipment doesn’t always equal a better job. A big trackhoe could make one pass up the center, clean the whole 15 foot and then throw the dirt way to the side where the little trackhoe is going to be tracking all over the place to get the same job done. A bigger trackhoe has bigger tracks so the ground contact isn’t much harder. Moving around hurts you more than anything.
 
   / Ditching job
  • Thread Starter
#96  
A scalpel requires a lot more money to avoid all the good tissue around the wound.

Is the owner prepared to pay for scalpel type work?
Yes it shouldn’t be in issue. They are super wealthy like you :)
They dont want speed and size.
Careful and easy does it
 
   / Ditching job #98  
You are the expert on everything . What is the big deal . Get a hoe and start winging that **** out in the field
 
   / Ditching job #99  
Smaller equipment doesn’t always equal a better job. A big trackhoe could make one pass up the center, clean the whole 15 foot and then throw the dirt way to the side where the little trackhoe is going to be tracking all over the place to get the same job done. A bigger trackhoe has bigger tracks so the ground contact isn’t much harder. Moving around hurts you more than anything.
This is what I’ve been saying. A big track hoe LOOKS like it will do more damage but it won’t. It will straddle the ditch and not be turning a lot. The hoe won’t tear things up near as much as moving the dirt away with your tractor.
 
   / Ditching job #100  
I’ve seen mats used and they do work. When I’ve seen the used though it was for very heavy equipment, like cranes used to install wind turbines, or to get something like a bull dozer across a highway.
 

Tractor & Equipment Auctions

Kivel 48in Pallet Fork Attackhment (A49251)
Kivel 48in Pallet...
2020 Utility Trailer Manufacturing, 53' Trailer (A47371)
2020 Utility...
2010 Ford E-150 Cargo Van (A46683)
2010 Ford E-150...
All Aluminum Service Body (A49251)
All Aluminum...
2013 Dodge Charger Sedan (A46684)
2013 Dodge Charger...
2013 John Deere 544K Articulated Wheel Loader (A46683)
2013 John Deere...
 
Top