LD1
Epic Contributor
Total ditch length approximately 1/2 mile.
Figured on working both sides, total of one mile, with small machine to minimize ground compaction
This is the info we were going off of.Just bid a good mile or more of ditching, double it if you count both sides
If the ditch is only 2640' total length.....15' wide, and 3' deep that is only a total of 2200yds of material......IF there werent already existing ditches.
So I'd say based on pics....that you are looking at excavating an approximate 1000yds of material total. This sounds way more plausible with a mini and a tractor with high capacity bucket.
With a ditching bucket a mini should be good for 25-30 yards per hour of material removal. So a good 40hr week give or take a bit.
From experience....using a mini to load a trailer, loader bucket, or anything other than just dumping in a pile is gonna slow you down big time. Gotta be slow, deliberate, and precise with your movements to not be banging into other equipment.
If the tractor can haul 2yds at a time and you can get 5 trips an hour.......thats 3 weeks of tractoring to build the berm. Still alot of seat time, but more doable without living on site for the next 3 months only shuttling dirt.
Get the mini in and out in a week. The tractor will quickly fall behind. But get the mini done and cut loose then use tractor for however long needed to shuttle the dirt.