At the risk of incurring a nasty-gram…From our meeting last night.... Dominion is our supplier.
"Virginians learned for the first time that Dominion has already signed agreements with data centers to provide over 13 gigawatts of additional power by 2038."
That 13gw is an additional 8 nuclear plants required, scaled off our largest plant, Lake Anna.
Since they cannot build power plants fast enough, they will have to use transmission services accordingly.
And Dominion is not the whole state. So the whole state is a pretty bleak picture of energy demand and supply currently and for the future.
EVs.