rademamj1
Veteran Member
- Joined
- Oct 8, 2019
- Messages
- 1,129
- Location
- Waco, Texas
- Tractor
- Kioti CK4010 SEHC, Kubota GR2120, Gravely Proturn 460
Around my area in Texas, we have a nasty clay formation right at the surface, probably 8-10 feet thick and covers hundreds of miles. They have now stopped using gravel base before the foundation pour, because over the years, the gravel being heavy will slowly work itself downward and into the underlying clay and thus rendering it ineffective. The number of foundation repair companies that have sprung up is incredible, and only a small number are truly qualified.
They have now moved to a select fill base, which is 80% fine grained clean sand and 20% silt. This is spread and compacted before the foundation pour and 10' beyond foundation limits. Over time, the select fill being same density does not drop down into the clay. Alot of foundations are now being done post tension cable, and so no rebar of any type is laid down. The verdict on using post tension is still not in yet. The theory is concrete in tension is strong, stable and crack resistant. So up to 48 or more 1/2" plastic sheathed cables are laid out at 16" spacing placed directly in middle of the concrete, one end anchored and the other end is extending 2' beyond the foundation. Three weeks later after the concrete is poured, a tension crew comes by and stretches those cables, placing the entire foundation in full tension. No expansion joints or saw crews are needed.
My building was done this way last June, and there were cracks in the foundation before the tension crew showed up. After they tension the slab, I noticed all visible cracks had closed. I preferred the rebar, but after a soil test my builder refused rebar and would only give warranty on Post Tension Slab.
They have now moved to a select fill base, which is 80% fine grained clean sand and 20% silt. This is spread and compacted before the foundation pour and 10' beyond foundation limits. Over time, the select fill being same density does not drop down into the clay. Alot of foundations are now being done post tension cable, and so no rebar of any type is laid down. The verdict on using post tension is still not in yet. The theory is concrete in tension is strong, stable and crack resistant. So up to 48 or more 1/2" plastic sheathed cables are laid out at 16" spacing placed directly in middle of the concrete, one end anchored and the other end is extending 2' beyond the foundation. Three weeks later after the concrete is poured, a tension crew comes by and stretches those cables, placing the entire foundation in full tension. No expansion joints or saw crews are needed.
My building was done this way last June, and there were cracks in the foundation before the tension crew showed up. After they tension the slab, I noticed all visible cracks had closed. I preferred the rebar, but after a soil test my builder refused rebar and would only give warranty on Post Tension Slab.