for your information on the previous 2 posts.
1. NEC requires 1 additional ground rod for 100 amp subpanel in separate building (2 rods for 200 amps). It doesnt matter that 4 wires were run. the ground rod is still required.
2. I usually lay out the wires out along side the trench first THEN slip the conduit onto the wires 10 - 20 feet at a time. This is done prior to dropping conduit into tranch. This way i can run 100's of feet of wire and conduit myself and never have to actually pull the wires. It works slick and saves alot of labor costs. If the conduits HAVE to be installed empty, then i always upsize the conduits otherwise youll be hating yourselves later on. (and i have the use of pullers and pulleys and it still sucks to pull thru tight conduits.)
You are right on the code requirements, and that is also the way I put the wire in the conduit. Much easier then pulling wire after.