Diggin It
Super Star Member
I have two ground rods within 5' of the house, 10' apart, connected with #6 THHN. Closest rod is connected to panel with #6 solid.
Shed/Barn out behind house has a 12/2 UF for power for some lights and general outlets. Planning on changing that to 10/2 at some point. Ground is provided that way, no separate ground rod.
LP tank is 100' from the house, out by the road. Gas line is poly/plastic, so no ground connection via pipe.
Considering a third ground rod at the house, but do I want it in a straight line from the others along the house? Or should it go out, away from the house, forming a T or L?
Do I need a ground rod out by the LP tank since it uses poly pipe and is not tied to any existing ground?
Do I need another ground rod at the shed tied to the ground of the UF?
Sketch is NOT to scale.
Shed/Barn out behind house has a 12/2 UF for power for some lights and general outlets. Planning on changing that to 10/2 at some point. Ground is provided that way, no separate ground rod.
LP tank is 100' from the house, out by the road. Gas line is poly/plastic, so no ground connection via pipe.
Considering a third ground rod at the house, but do I want it in a straight line from the others along the house? Or should it go out, away from the house, forming a T or L?
Do I need a ground rod out by the LP tank since it uses poly pipe and is not tied to any existing ground?
Do I need another ground rod at the shed tied to the ground of the UF?
Sketch is NOT to scale.