Help me out fellas, this is my 1st time around on this. I'm having a barn/garage constructed and think I have finalized my specs. Here they are:
30’ x 40’ Garage/ Barn Specifications
1. 4” thick slab with 12” x 12” perimeter beams with rebar Smooth surface (to be painted later by me).
2. 3’ x 8’ covered and walled compressor shed.
3. 3’ sidewalk 40’ long along side nearest house.
4. Plumbing in slab to accommodate sink and toilet.
5. plumbing for electrical service.
6. Red iron bolt up construction.
7. 3/12 pitch roof.
8. Insulated with vinyl backed 3” thick fiberglass insulation.
9. 12’ tall walls All siding and roof to be 26 guage R panels, 30 year warranty
10. Light tan/beige colored side walls. Dark green trim and rain gutters.
11. White colored roof.
12. Rear side to be framed for 10’ x 10’ Roll up type door on south end. (I have one already). Front side (north) framed for 18 x 8 garage door
13. Walk in 48” metal door at walkway with deadbolt lock.
14. Cutout trimmed for window AC unit
15. Full clean up after job is done.
What am I leaving out? What am I going to be kicking myself saying "How stupid- What was I thinking, why did I not include_________???
Thanks for any advice....Kyle
30’ x 40’ Garage/ Barn Specifications
1. 4” thick slab with 12” x 12” perimeter beams with rebar Smooth surface (to be painted later by me).
2. 3’ x 8’ covered and walled compressor shed.
3. 3’ sidewalk 40’ long along side nearest house.
4. Plumbing in slab to accommodate sink and toilet.
5. plumbing for electrical service.
6. Red iron bolt up construction.
7. 3/12 pitch roof.
8. Insulated with vinyl backed 3” thick fiberglass insulation.
9. 12’ tall walls All siding and roof to be 26 guage R panels, 30 year warranty
10. Light tan/beige colored side walls. Dark green trim and rain gutters.
11. White colored roof.
12. Rear side to be framed for 10’ x 10’ Roll up type door on south end. (I have one already). Front side (north) framed for 18 x 8 garage door
13. Walk in 48” metal door at walkway with deadbolt lock.
14. Cutout trimmed for window AC unit
15. Full clean up after job is done.
What am I leaving out? What am I going to be kicking myself saying "How stupid- What was I thinking, why did I not include_________???