Diggin It
Super Star Member
This wouldn't be much of a project for most of you, but remember, I only have a pipsqueak of a tractor.
Slab is a little less than 3' x 5' and roughly 3-4" thick. As I recall, it took either 10 or 11 80lb bags. I know I can't lift it fully off the ground. Not even gonna try. Might be possible with the 3pt if I had the right rigging, which I don't. Specs say 966 pounds, but I don't know how I'd rig it to lift.
Plan is to lift a corner (FEL should handle that) enough to get a steel cable under it; repeat on the other end. Use the cable to drag the slab. Not sure if I can do that with the FEL or if it would risk torquing something. Will probably try using the rear drawbar.
It only has to go about 15 feet, but has to be turned 90 degrees. New location is set, series of concrete blocks as a perimeter. They're partially filled with concrete, then leveled with crushed rock and the center area is filled with crushed rock.
Plan is to position the slab to one side, then set 2 x 4s to use as slides to drag the slab into place. Lift and remove the 2x4s.
How far off am I?
Ground is too muddy now, so this is several days out. Figure I need 3-4 dry days before I can start and those dry spells have been very few and far between in recent months.
Edit .....
Of course, the other option is to pour another slab for about $45-50 or so at $4-something a bag. The existing slab is sort of in the way, but could be worked around.
Slab is a little less than 3' x 5' and roughly 3-4" thick. As I recall, it took either 10 or 11 80lb bags. I know I can't lift it fully off the ground. Not even gonna try. Might be possible with the 3pt if I had the right rigging, which I don't. Specs say 966 pounds, but I don't know how I'd rig it to lift.
Plan is to lift a corner (FEL should handle that) enough to get a steel cable under it; repeat on the other end. Use the cable to drag the slab. Not sure if I can do that with the FEL or if it would risk torquing something. Will probably try using the rear drawbar.
It only has to go about 15 feet, but has to be turned 90 degrees. New location is set, series of concrete blocks as a perimeter. They're partially filled with concrete, then leveled with crushed rock and the center area is filled with crushed rock.
Plan is to position the slab to one side, then set 2 x 4s to use as slides to drag the slab into place. Lift and remove the 2x4s.
How far off am I?
Ground is too muddy now, so this is several days out. Figure I need 3-4 dry days before I can start and those dry spells have been very few and far between in recent months.
Edit .....
Of course, the other option is to pour another slab for about $45-50 or so at $4-something a bag. The existing slab is sort of in the way, but could be worked around.
Last edited: