EddieWalker
Epic Contributor
We are night and day apart on this. For fill to compact, it must bond to itself. It must hold moisture, and it must be a certain level of moisture for it to compact.I would never ever use any soil as a fill for a concrete foundation because of the high organics. The best choice is a select fill, which has been washed and is free of organics, and is fine grained trending mostly to a silt sized particle. You typically find these type fills in river bends where large and now exposed silt bars are deposited and the naturally washed and recovered fill is sold by truckloads. It is relatively dry to visual eyes, but it does retain water by surface adhesion on each silt particle, giving a perfect moisture content for the overall select fill.
Compaction of such a selected fill occurs very well using a typical 10,000lb tracked skid steer. But you should spread and compact with each truck delivery, not dump say 20 truck loads first and then spread and compact all of it. Even wheeled vehicles struggle greatly when that occurs, resulting in uneven compaction surfaces. Usually you can build such a foundation as fast as the trucks deliver, or about 1 to 2 days.
Clean fill is the soil that does not have top soil. Top soil is where leaves and plants have deteriorated and are breaking down. Here in East Texas, where I live, we do not have top soil, just a layer of organics that are cleaned off. How deep the top soil is depends on location, but once you remove it, the clean fill is the dirt that is found under the top soil.
Every machine with tracks is designed to float over the ground. It has the very minimal PSI possible. It is the very worse machine possible for compaction. Using a light weight 10,000 pound machine doesn't even make sense.