After a long delay, Stan, the pond man, called Wed. afternoon and asked to meet me onsite Thur. to discuss the plan to make sure we where on the same page. I took a few pictures of the dry pond.

The first picture shows the east bank and the northern end of the pond. It also shows the island but it's hard to see. The east bank will not change. Fill will be added to the right of the bank since that area is lower than the bank and stays wet if and when we have rain.

We're in an extreme drought now. The experts say we're having the driest May on record. I was curious as to why there was a large bare area here. I took a shovel and tried to dig a hole and saw that there was about a half inch of sediment and then pure hard clay.

The second picture shows the dam. It will be de-constructed. The new dam will have a larger footprint and constructed properly, i. e. cored, wider base and top, etc.

The third picture was taken from the dam looking northeast. It also shows the island. Some of the old longleaf pine stumps still have the notches in them from when the turpentine was harvested. The north end was very shallow, swampy, etc. Stan couldn't give us a firm quote until he "uncovered" the north end to see what had to be done.
 

Attachments

  • DSC00942.JPG
    DSC00942.JPG
    563.1 KB · Views: 473
  • DSC00943.JPG
    DSC00943.JPG
    607.5 KB · Views: 471
  • DSC00944.JPG
    DSC00944.JPG
    612.4 KB · Views: 435
/ Pond re-do Part 2 #2  
Hi Bart,

I had missed Part 1 so I went back and read that first. Looked like a beautiful pond, so I'm sure any improvements will make it that much better! I'm looking forward to following the "re"construction.

Although you're in a drought now, are you concerned about getting it filled back up again over time?
 
/ Pond re-do Part 2
  • Thread Starter
#3  
Although you're in a drought now, are you concerned about getting it filled back up again over time?

Hi Kevin,

No, I'm not really concerned. There, apparently, was enough acreage that drained to the old pond to bring it up to full level. Also, I saw water running thru the spillway several times in the past. When Stan broke the dam last Sep. he dug 2 test holes below the dam. The holes immediately began to fill with water so there was significant leakage thru/under the dam. Michele and Tony don't plan to move on site for another 5 years. It will be interesting to see how long it will take to fill.

So Friday morning I was at home doing my thing when Stan called. He asked me to come right over since he had the north end and part of the west side cleared. He also had the water line staked on the east, north, and part of the west sides. DW volunteered to go to keep me company.

I'll attached a few pictures to show the progress.

The first is of the old spillway. He said he was going to have to rebuild it. The top of the pink flags will be the high water mark.

The next 2 will show the east side and then a couple of the north, then west. I'll include a couple of action shots and then the site of the former island.

Initially we had told Stan to take out all of the volunteer pecan trees. But he had uncovered 3 pretty ones and since they would not be in the way, he suggested we leave them. I agreed.

The last picture is of DW reading her Kindle.
 

Attachments

  • DSC00954.JPG
    DSC00954.JPG
    592.5 KB · Views: 239
  • DSC00953.JPG
    DSC00953.JPG
    572.7 KB · Views: 291
  • DSC00952.JPG
    DSC00952.JPG
    600 KB · Views: 325
  • DSC00951.JPG
    DSC00951.JPG
    603.8 KB · Views: 329
  • DSC00957.JPG
    DSC00957.JPG
    567.2 KB · Views: 243
  • DSC00958.JPG
    DSC00958.JPG
    581.9 KB · Views: 251
  • DSC00959.JPG
    DSC00959.JPG
    608.7 KB · Views: 259
  • DSC00970.JPG
    DSC00970.JPG
    962.8 KB · Views: 262
  • DSC00966.JPG
    DSC00966.JPG
    595.4 KB · Views: 314
  • DSC00962.JPG
    DSC00962.JPG
    595 KB · Views: 256
  • DSC00969.JPG
    DSC00969.JPG
    594 KB · Views: 358
/ Pond re-do Part 2 #4  
Bart, glad you are updating the project. I enjoyed the big fish catch from your first post. One question I had was about pond weeds. If that was a problem in the original pond you may want to take advantage of the work now to help with that in the future. You mentioned the east bank remaining as is and it has a gradual slope. Pond managers often recommend a steeper slope to gain depth closer to shore and cut the sunlight that promotes pond weeds. Of course if that hasn't been a problem it doesn't matter.

If you haven't in the past take a look at Pond Boss Magazine: Welcome They have a forum with a great deal of information on building and renovating ponds.

MarkV
 
/ Pond re-do Part 2
  • Thread Starter
#5  
I got ahead of myself in telling the story. On Thur. I took a couple of pictures of an area that has been troublesome for our neighbour, Greg. Property to the west of him drains to his small pond and his pond overflows and drains thru a culvert under the county road to our side.
I have come to believe the county road crew is somewhat road maintence challenged. Every now and they come thru with a grader and, either, fill in the ditches or leave a ridge on both sides of the dirt road. I have never seen a crown. Once in a great while they will come back and dig out the ditch and the process starts over again. In the past they have caught the end of the culvert and ripped of the end when they cleaned out the ditch. Bit by bit, and now the culvert is 3 - 4 feet shorter than it should be. When ever the grader comes thru and is in the "filling-in-the-ditch" mode, the end of the culvert gets covered up, thus the water doesn't drain from Greg's property.

The power company has recently whacked back the overgrowth from their easement and the road crew has recently cleaned out the ditch. A fairly deep ditch, running into the woods on the north end of the pond, was revealed. Also, there are many yards of sand stacked, by the road crew, on the easement and also on into the property.

Stan is going to build up this area, install a 20' x 24" culvert, and a sand trap between the road and culvert. The culvert will allow east field to west field access on the north side of the property.

The first 2 pictures show the culvert and ditch area. While I was there on Fri. the county grader made a couple of passes. :)
 

Attachments

  • DSC00946.JPG
    DSC00946.JPG
    589.2 KB · Views: 296
  • DSC00947.JPG
    DSC00947.JPG
    615.2 KB · Views: 281
  • DSC00961.JPG
    DSC00961.JPG
    567.8 KB · Views: 272
/ Pond re-do Part 2 #6  
Great Project! My pond probably has waist deep silt in it in areas. It is rather long and narrow but about 2 acres. I wish I had the money to get an old dragline to deepen it. I was thinking with a helper, using a 4wd tractor and big box blade to scrape the spoils over to a low area, I could get it done without draining. I know it would get messy, I'd probably just have to put the spoils in a continous "ridge" behind me as I work forward. After drying time, maybe then I could spread it out. Has anyone spread silt over their fields? I'm wondering if it is very detrimental assuming it is anerobic....Talk about pond scum...:laughing:
 
/ Pond re-do Part 2 #7  
Great project and perfect timing. Dig while the digging is good and dig as much as you can get out before it gets wet again!!!!!

Eddie
 
/ Pond re-do Part 2
  • Thread Starter
#8  
Mark,

Yes, the old pond had a weed problem in the northern third, around the island, and the first few feet along the bank. Stan said the there will be a minimum 3' depth in the new pond. Most of the pond will be much deeper with a few deep holes.

The pond boss site has been mention on this forum many times and I have been there a couple times. But there's several things going on with this project:

I'm not the owner of the property, just volunteering to help my daughter and SIL. What little I know about ponds is what I have read on this forum (Eddie's thread for instance ).

Dau. and SIL are absentee owners and both have very demanding jobs.

Stan's main business is building ponds including "government ponds" (his words, i.e. cost sharing with property owners). By the way, this is not a government pond. He is well known for his work and was highly recommended.

There is no written contract for this project. Things still get done with a handshake in this neck of the woods. This can be dangerous and we almost had a "slip up". Probably would offend someone if we insisted on a written contract. No money has changed hands yet.

I'm a certified, card-carrying senior citizen and am just doing the best I can. :confused2: My goal, in helping with this project, is to help ensure that nothing major falls thru the cracks and make recommendations to my Dau., who makes the decisions and pays the bills, that will make it a good pond.

I appreciate yours and everyone else's comments and help. Thanks!

Kyle,

That's funny. I was thinking the same thing about the silt. I thought I would bring home a few buckets of it and see how things would grow in it. That's why I had the shovel, mentioned earlier, with me. One concern was how much Ag chemicals were in the silt. I think I'll just buy some top soil when I need it.

Eddie,

Yes, Stan waited a good while to make sure it had dried up and he is going to complete the north end first. That's the part that will get the most run off first and stay the wettest if it ever rains again. Now he says there might be a delay in coring the dam since the clay is too dry and won't pack down. It figures.

Thanks for everyones' interest.
 
/ Pond re-do Part 2
  • Thread Starter
#9  
I have another update with pictures. :)

Last Friday, when I was discussing the situation with Stan, he mentioned he was going to change the spillway a bit. The spillway was designed to handle normal and emergency overflow. It was quite elaborate and probably was quite scenic at one time as it was lined with brick, rock, and concrete block. It has a small dam made of block, re-enforced with rebar and concrete.

But the spillway was a source of irritation since going thru it was the main route to the dam. It stayed wet a good bit of the time which also made it difficult to mow. The area between the little dam in the spillway and the pond could not be mowed at all.

Part of the spillway, on the outside of a curve, was line with large, dry-stacked concrete block. I thought it would be a great waste for these blocks to be buried in a hole so decided to salvage them.

Brother Warren (who's no spring chicken, either) volunteered to help and I hired his stepson's wife's twin sister's husband, Scott, to help. :) Scott is a fellow Marine vet who served 4 years active duty and 5 years active reserve. He was called up while in the reserve to "visit" Kuwait and Iraq. He felt like close kin to me.

Shortly after we started, neighbor, Greg, showed up with his Ford with forks. Told us to go ahead and use it and try to pop out the blocks with the forks. He said he might come back to check out the progress. I asked Warren to do the tractoring since he has more experience and, also, he's an Ag engineer (and acts like it, too :laughing:). After Greg showed him the quirks (no brakes, etc.), he left to go do his thing and never came back. Probably a good thing too 'cause, by the time we were done, we each would have given him a hug and a kiss. :eek:

Anyway, here's a couple of pictures of us gettin' it. It took us 4 hours and we salvage 88 block. Also, a few pictures of Stan's progress. The last picture shows the culvert under the road, that I mentioned in an earlier post, area.

I'm going to central fLa. for a few days so won't be able to be "onsite" until next Monday.
 

Attachments

  • DSC00980.JPG
    DSC00980.JPG
    588.6 KB · Views: 302
  • DSC00981.JPG
    DSC00981.JPG
    596.1 KB · Views: 360
  • DSC00988.JPG
    DSC00988.JPG
    603.9 KB · Views: 221
  • DSC00987.JPG
    DSC00987.JPG
    523.2 KB · Views: 218
  • DSC00986.JPG
    DSC00986.JPG
    588.5 KB · Views: 217
  • DSC00985.JPG
    DSC00985.JPG
    601.1 KB · Views: 227
  • DSC00989.JPG
    DSC00989.JPG
    595.3 KB · Views: 251
  • DSC00990.JPG
    DSC00990.JPG
    586.5 KB · Views: 256
  • DSC00996.JPG
    DSC00996.JPG
    587.1 KB · Views: 297
/ Pond re-do Part 2
  • Thread Starter
#10  
The pond project was completed in June but I'm just now making the time to show the rest of the story.

My brother and I went over there on the 6th to check on the progress. Stan had pretty much completed the final grade on the east, north, and most of the west bank, and was now roughing in the dam.

The first picture is of the east side and shows where Stan filled in the low area with clay. He will cover up the clay with top soil. The 2nd shows part of the north and west.

3rd and 4th shows the back and front sides of the roughed in dam.

The next 3 are some action shots of Stan. That would give me the willies.

A picture of my brother standing next to an old longleaf pine stump and lastly, a picture of the cleaned out spillway.
 

Attachments

  • DSC01016.JPG
    DSC01016.JPG
    608.5 KB · Views: 335
  • DSC01013.JPG
    DSC01013.JPG
    603.3 KB · Views: 264
  • DSC01010.JPG
    DSC01010.JPG
    572.3 KB · Views: 270
  • DSC01008.JPG
    DSC01008.JPG
    580.9 KB · Views: 254
  • DSC01037.JPG
    DSC01037.JPG
    588.5 KB · Views: 299
  • DSC01033.JPG
    DSC01033.JPG
    589.2 KB · Views: 259
  • DSC01031.JPG
    DSC01031.JPG
    610.8 KB · Views: 342
  • DSC01032.JPG
    DSC01032.JPG
    590.3 KB · Views: 321
  • DSC01034.JPG
    DSC01034.JPG
    582.9 KB · Views: 282
/ Pond re-do Part 2
  • Thread Starter
#11  
I'm went back a few days later to see the progress. I took a bunch of pictures during this project and I'm finding it difficult to decide which ones might be interesting to others and not bore anyone.

Anyway, it's the core-the-dam phase of the project. Stan was concerned that the clay may be too dry for it to pack down for the core but it rained just enough for that not to be a problem. He subed out the dirt pan work. I was told the dirt pan's capacity was 14 yards. The east half of the core was built up first, then the west half.

I did not get to see the core at its deepest but the neighbor took his wife on their 4 wheeler thru it and she told him to get her out of there, NOW!

Stan had determine that the clay on the east side of the pond was better than the clay on the west side. The dirt pan operator went round and round for several days building up the core. The 2nd to last picture shows just a bit of the left corner of the dirt pan.
 

Attachments

  • DSC01039.JPG
    DSC01039.JPG
    570.2 KB · Views: 221
  • DSC01043.JPG
    DSC01043.JPG
    595.2 KB · Views: 197
  • DSC01044.JPG
    DSC01044.JPG
    580.8 KB · Views: 223
  • DSC01045.JPG
    DSC01045.JPG
    555.4 KB · Views: 226
  • DSC01061.JPG
    DSC01061.JPG
    590.1 KB · Views: 184
  • DSC01056.JPG
    DSC01056.JPG
    582.5 KB · Views: 209
  • DSC01053.JPG
    DSC01053.JPG
    511.5 KB · Views: 199
  • DSC01048.JPG
    DSC01048.JPG
    575.4 KB · Views: 261
  • DSC01067.JPG
    DSC01067.JPG
    575.9 KB · Views: 213
  • DSC01068.JPG
    DSC01068.JPG
    551 KB · Views: 199
  • DSC01069.JPG
    DSC01069.JPG
    609.8 KB · Views: 276
  • DSC01075.JPG
    DSC01075.JPG
    602.1 KB · Views: 230
/ Pond re-do Part 2
  • Thread Starter
#12  
Back 6 days later...

The moving of dirt is, for most part, over. The 1st and 2nd pictures show the east and west ends of the dam.

The next 4 show the siphon/overflow system being installed.
Then a picture of the spillway for emergency overflow, a fish hole, the back side of the dam and we had more rain.
 

Attachments

  • DSC01092.JPG
    DSC01092.JPG
    589.1 KB · Views: 242
  • DSC01082.JPG
    DSC01082.JPG
    599.8 KB · Views: 209
  • DSC01087.JPG
    DSC01087.JPG
    616.2 KB · Views: 199
  • DSC01079.JPG
    DSC01079.JPG
    588.6 KB · Views: 219
  • DSC01120.JPG
    DSC01120.JPG
    612.1 KB · Views: 209
  • DSC01099.JPG
    DSC01099.JPG
    600.1 KB · Views: 193
  • DSC01105.JPG
    DSC01105.JPG
    540.2 KB · Views: 213
  • DSC01095.JPG
    DSC01095.JPG
    596.5 KB · Views: 238
  • DSC01122.JPG
    DSC01122.JPG
    585.4 KB · Views: 199
  • DSC01129.JPG
    DSC01129.JPG
    554.4 KB · Views: 203
/ Pond re-do Part 2
  • Thread Starter
#13  
I went back 2 days late on the 18th of June. Straw was being scattered out. 1,000 lbs./acre of lime had been spread in and around the pond. Also, 100 lbs./acre of balanced fertilizer was spread around the pond and brown top millet and common Bermuda had been drilled.

Oh, we had more rain. The last picture shows the new pipe installed below the dam to make it easier to cross over from the east side to the west.
 

Attachments

  • DSC01143.JPG
    DSC01143.JPG
    567.9 KB · Views: 242
  • DSC01142.JPG
    DSC01142.JPG
    604 KB · Views: 224
  • DSC01140.JPG
    DSC01140.JPG
    608.2 KB · Views: 215
  • DSC01138.JPG
    DSC01138.JPG
    607.1 KB · Views: 218
  • DSC01146.JPG
    DSC01146.JPG
    616 KB · Views: 247
/ Pond re-do Part 2 #14  
That's going to be an awesome pond. I can't wait to see it filled
(refilled).:thumbsup:
 
/ Pond re-do Part 2 #16  
Wow, that's gonna be a nice pond. Have you figured up the acreage? Or is it posted somewhere and I just got picture happy.....:)
 
/ Pond re-do Part 2
  • Thread Starter
#18  
Thanks to all for the compliments. We were fortunate to have some great folks that helped get this project done: Stan, the pond man, Dale, the NRCS guy, and Greg, the neighbor. Also, lady luck was player, i.e. it didn't rain or it did rain just at the right times.

Kyle, The size of the pond was estimated at 3 acres but it sure looks bigger than that to me. My home is on a 300' x 300' lot and the pond looks to me like at least 2 of my lots could fit in it. But looks can be deceiving especially since my lot is wooded.

Dau. and SIL drove down 4th of July week for a visit and to check out the new pond. They were pleased with the results and now will try to figure out the best spot for their future home and then where to build the barn.

The millet seem to just leap out of the ground! I've attached a few pictures. :)

I'll upload a couple pictures when the pond is filled.
 

Attachments

  • DSC01161.JPG
    DSC01161.JPG
    612.2 KB · Views: 222
  • DSC01159.JPG
    DSC01159.JPG
    547.5 KB · Views: 211
  • DSC01151.JPG
    DSC01151.JPG
    581.2 KB · Views: 212
  • DSC01149.JPG
    DSC01149.JPG
    557.7 KB · Views: 249
  • DSC01162.JPG
    DSC01162.JPG
    606.6 KB · Views: 217
  • DSC01176.JPG
    DSC01176.JPG
    586 KB · Views: 266
/ Pond re-do Part 2
  • Thread Starter
#19  
It's time for an update.

I took up bike riding last year for theexercise and thought it would be swell idea to buy a Garmin GPS Edge 200 for the bike. It has the normal bike computer functions plus you can upload the route ridden. Garmin software overlays it on a map/satellite image. I can now see on my pc where I've been. :)

I know this is a bit lame but... I took my bike GPS over to the pond. I drove the gator slowly, counter clockwise, as close to the edge of the pond as I dared, while holding the GPS with my left arm outstrecthed. I don't know why the starting and ending points did not match up. Maybe the earth shifted a bit. But I came up with a circumference of .28 miles. Using that figure and a couple of conversions here and some round offs there, I came up with the area of the pond of 3.99 acres.

Of course I had to make some assumptions, like the pond is a circle, etc, but I'm positive that, given my mathematical skills and such, it would be safe to say that the area of the pond is between 2 and 6 acres, but I'm just going to say the pond is 4 acres. The picture shows the property with the old pond.

Pond area via GPS.jpg

A friend of Michele's just happened to be flying by and took some pictures of the property. There is some water in the new pond. The road at the bottom of the first picture runs almost true north to south. The southern property line is to the right of the mowing lane, row of cedars then a thin row of native trees. It's a straight line on through the hardwood bottoms. The new dam is close to the center of the picture.

The second picture is from the east. The eastern property line is a straight line right at the clear cut area to the road on the right.

Sycamore04.jpg Sycamore12.jpg
 
/ Pond re-do Part 2
  • Thread Starter
#20  
Greg, the neighbor, called Michele last Monday morning and told her the pond was beyond full after the 9 inches of rain we had last week (through Sunday). He sent her a few pictures that he took Monday morning. The following picture shows the water coming out of the overflow pipe.

image.jpg

I went over yesterday to check it out and took a few pictures. The first of 4 pictues is of the east side then working towards the west. The 5th picture was taken close to the west end of the dam. The first picture, from the debri on the bank, shows the high water mark, about a foot above the max, normal level. Water was up in the emergency overflow spillway about 15 feet.

DSC01278.JPG DSC01274.JPG DSC01275.JPG DSC01277.JPG

Edit: I messed up loading the 5th picture. The 2nd pic is the one starting on the east side. The 1st on shows the dam from the east side.

Water was still coming out of the overflow pipe and the small pipe was sucking a little air then the water would cover the end of it.

DSC01279.JPG DSC01280.JPG
 

Attachments

  • DSC01276.JPG
    DSC01276.JPG
    529.1 KB · Views: 180
Last edited:
 
Top