Underground Electrical Service Question

   / Underground Electrical Service Question #11  
Many years ago when I put in my meter, there was no specification on having a slip joint or other means for ameliorating the effects of heave. So I mounted the meter (which comes up by itself between the ground mounted transformer and the house) on a plate with machined vertical slots, having lags going through the slots to the mounting wood. Basically I figured I needed something and rolled my own. Now they have codes to cover the potential problem.

The slots are only 2-3" long, and I've had to remount the lags a couple of times between heave and settling of the 5' deep trench.

If I had to do the underground over again, the one thing I'd do is check different secondary conductors, one brand of 4/0 was way stiffer than the other brand, causing a lot of extra effort for installation. I had figured they'd all be about the same... one brand worked reasonably easily in 2" LBs, other one was a PITA (with a mallet) [used sweeps outside, but inside needed LBs to drop to the distribution panels.].
 
   / Underground Electrical Service Question #12  
My utility wanted a pull rope installed and some even want the official thing (can't remember the name) pulled through to prove the conduit is clear.
.
Mandrel is the word for today, that is if I spelled it right....
 
   / Underground Electrical Service Question #13  
Captain,

Yeah, I think that's it. Thanks.

A short cable with eyes on each end and a few very thick flat washers in the middle.

Sheesh, brain fade.


John
 
   / Underground Electrical Service Question #14  
Captain,

Yeah, I think that's it. Thanks.

A short cable with eyes on each end and a few very thick flat washers in the middle.

Sheesh, brain fade.


John
John, Your quite welcome... I can't get the word "Mandrel" out of my mind, after running a job installing a several new underground services for a Hospital in Annapolis, Maryland... Power Co. required a mandrel to be pulled in all PVC conduit.. Installed about 15,000' of 6" PVC conduit and pulled a 6" mandrel in all the conduit...
 
   / Underground Electrical Service Question #15  
Wow things are different from state to state. I had to run 1400' of service line to the meter then another 350' from the meter to the house. In Vermont (or maybe it was a power company requirement) the service line had to have a vault every 600'. I could do the trenching and install the 2 1/2" conduit but they provided and installed the cable. they also installed a transformer on top of the last vault and ran the wire to the meter.

From the meter the power company no longer cared. In VT there is no inspection so you can do what you want from the meter on but when you go to sell the house if it's not to code good luck. I figured it out on my own but a good friend is an electrician so before I did anything. For me, 200 amp service and a run of over 300' 4/0 alum is not thick enough so I had to go with mcm350 (it's been a few years so I could be off a little). But I think code was the outside diameter of cable could only be 40% of the inside diameter of the conduit so I had to use 3". I also had to use slip joints everywhere the conduit penetrated the ground where it could freeze. Since the conduit comes into the house through my cellar slab I didn't need one there but everywhere else I did. I think my buddy said the 40% rule was to allow the wire to move inside the conduit to compensate for the frost movement.

The service line to the meter had to be 3' down and if anything else was to be buried in the same trench it had to be at least 1 foot apart. It was either 1' or 2' down there needed to be a red "warning powerline" tape buried into the hole. On the house side it only had to be 2' down.

I would go to a local electrical supply shop (not Lowes) and ask. They may be able to help you or know of an electrician who will give you answers for a reasonable price (I doubt you'll find free unless you know one).
 
   / Underground Electrical Service Question #16  
I would also note the 90s, or sweeps come in two styles. There are tight or sharp bends and then a more gradual style. If I remember correctly I couldn't use the sharp bends, something about pulling cable through them.

Again I did my house and just recently my garage myself but would recommend you talk to a pro. There are rules of thumb as to what size wire you need for the service load you are installing all over the internet but the correct way is to figure it out with max current vs distance. Doing it wrong, even if no inspection is required, could prove very costly even if it's able to handle the load you put on it without a problem.
 
   / Underground Electrical Service Question #17  
crazyal, I left out the 2 piece (1600 lb each) vaults and the Power Co. pulled in their high voltage wire.. Vaults were no more then 600' apart...
 

Tractor & Equipment Auctions

2022 Down2Earth 82in x 36ft Two-Car Hauler (A46884)
2022 Down2Earth...
4- 5TH WHEEL RAILS (A47001)
4- 5TH WHEEL RAILS...
Blue Concrete Test Shed (A45336)
Blue Concrete Test...
1671 (A44572)
1671 (A44572)
FLAT BED FOR TRUCK (A47001)
FLAT BED FOR TRUCK...
2016 KENWORTH T680 SLEEPER (A43005)
2016 KENWORTH T680...
 
Top