Water line bid

   / Water line bid #21  
JRobyn said:
Hey Eddie,

The $3600 includes the 2" gates ($190 each with flange kits). The trenching is the issue; the property is almost solid rock, so they'll use a "rock trencher" (the county permit man tells me it cost the contractor about $100k). The bid includes 10 days of trenching = $10k. They acknowledge that it should take less and they've provided a worst case estimate. Then there's $3k worth of trencher teeth too!

That certainly explains it. There is some rock that even trenchers have issues with. I had wanted to take some pictures of a pair of trenchers up my way they used for sewer line, power and other utilities when cutting through lava cap. They were beasts. Each trencher looked like it could cut a path about 40" wide and about 20' deep. They were the size of a D9 doubled.
 
   / Water line bid
  • Thread Starter
#22  
Hey RaT,

I'll try to post some pics of their trencher, assuming that I decide to have them run the line. They tell me it cuts a 8" trench up to 42" deep. We'll only need to bury my line 24". To my surprise, they mentioned that SOFTER rock is often more difficult to cut! That makes me nervous, because our rock is "shale rock"; it's quite hard, but is very "flakey". I'm keeping my fingers crossed that the trenching is way less than 10 days so that the price drops!
 
   / Water line bid #23  
JRobyn said:
Hey Eddie,

The $3600 includes the 2" gates ($190 each with flange kits). The trenching is the issue; the property is almost solid rock, so they'll use a "rock trencher" (the county permit man tells me it cost the contractor about $100k). The bid includes 10 days of trenching = $10k. They acknowledge that it should take less and they've provided a worst case estimate. Then there's $3k worth of trencher teeth too!

So you have roughly $4K in materials and $10K for the trencher. Where is the other $15K?

We are on a hill and our neighbors are downhill from us. The nearest house has over 30 GPM. That well had water flowing out of the pipe for weeks after it was drilled. Our well is 15 GPM and we are a good 2000 feet from the 30 GPM well. There is another well withing 300 feet of the 30 GPM well and I think they are around 5 GPM. These wells are on the east side of the road. On my side the nearest well is about 1500 feet away and roughly in line with ours but he is another 5 GPM. I figured we would be lucky to get 5 GPM but we got 15. I think the well are all go to 200 to 300 feet.

The point I am trying to make is that its a roll of the dice as to what you get even if the wells are real close. My understanding is that in my area its very unusual to get a dry hole.

Have you talked to the county office that permits well drilling to see what they say about hitting water? How many people have problems hitting water or getting enough water?

Later,
Dan
 
   / Water line bid #24  
Jackie Houston did our well, we never discussed a gaurantee, he just said, he had drilled a lot of wells in my area and knew that we would hit. We hit water at 125ft and he went to 200' but the flow rate is only about 1-2 gpm, so I had him go to 300 ft (an additional $800) we did not hit any more water at that depth, but we now have about a 200 gallon storage.

As for the trenching issue, I did the trenching for all my water, sewer and electric lines myself. I rented a walk behind trencher from RSC ($350 for a week) and did over 500' of 36" trenches in between other jobs here that week. Actual trenching time about 20 hours. I would check with the RSC in Cookeville to see what they have available, I know the one in Crossville has the ride on type that go for about $300 a day but the weekly rate is under $1000. We have 3 other places here that rent large equipment and I'm sure there are even more in the Cookeville area.
 
   / Water line bid #25  
Harleymsn said:
Jackie Houston did our well, we never discussed a gaurantee, he just said, he had drilled a lot of wells in my area and knew that we would hit. We hit water at 125ft and he went to 200' but the flow rate is only about 1-2 gpm, so I had him go to 300 ft (an additional $800) we did not hit any more water at that depth, but we now have about a 200 gallon storage.

As for the trenching issue, I did the trenching for all my water, sewer and electric lines myself. I rented a walk behind trencher from RSC ($350 for a week) and did over 500' of 36" trenches in between other jobs here that week. Actual trenching time about 20 hours. I would check with the RSC in Cookeville to see what they have available, I know the one in Crossville has the ride on type that go for about $300 a day but the weekly rate is under $1000. We have 3 other places here that rent large equipment and I'm sure there are even more in the Cookeville area.

The problem is, none of those trenchers will go through rock. When you hit rock, the price will skyrocket. I've seen large excavators with hydraulic hoes unable to get through rock. It needed to be fractured first.
 
   / Water line bid #26  
JRobyn said:
Hey RaT,

I'll try to post some pics of their trencher, assuming that I decide to have them run the line. They tell me it cuts a 8" trench up to 42" deep. We'll only need to bury my line 24". To my surprise, they mentioned that SOFTER rock is often more difficult to cut! That makes me nervous, because our rock is "shale rock"; it's quite hard, but is very "flakey". I'm keeping my fingers crossed that the trenching is way less than 10 days so that the price drops!
I take it from what you are posting that you are NOT from the area, and I fear that this contractor knows that. I can't speak for Gainesboro myself, but most of the rock in this area is not shale. In any event, I have a friend that is in the rock business here (he digs out and sells rock or stone for building, as we have some of the best in the country here) he has been working a lot in the Livingston area for the past year and does it ALL with a Case 40XT skid steer with a 4' smooth bucket. When I first bought my land here, I was told all the horror stories about the rock here ..... soil top is only 18", you'll have to blast through the rock for everything ... septic, foundations, trenching etc.
When they did my well, they did not hit any rock until they were down 12'.
I did all that trenching here and didn't hit anything larger than maybe a 2' diameter rock, and there were very few of them.
Before I signed on the dotted line, I would talk to a few people in the area, stop at a couple of equipment rental outfits and question them, they may have more intel for you that the contractors want you to have.
 
   / Water line bid
  • Thread Starter
#27  
Dan,

Here's the rough breakdown (both waterline/trench and road grade/gravel):

$4k - piping and mat'ls
$10k - 10 days trencher @ 10hr/d
$4k - 10 days bulldozer @ 5 hr/d
$3k - 10 days backhoe @ 5 hr/d
$3k - 10 changes of trencher teeth
$2k - 10 days misc labor
$3k - 20 loads creek gravel

We have discussed the local well situation with every resident that has one around the entire perimeter of our property. This includes about 6 or 8 wells within 1/2 mile or less. All of them are relatively low-flow. One has recently stopped producing entirely. That's the neighbor that had another one drilled on that propery, plus a second new DRY one on another parcel he recently bought. Typical water depth is about 75-100ft below the surface depending on the specific elevation, so I assume that they are all in a "related" aquifer. Drilling below about 150-200 ft can reportedly result in very sulfurous water. So we're fairly well (pun intended) aquainted with the local conditions.

Joe,

RaT is right about the rock.... and there's no question about how much of it there is or where it is since the existing road bed is essentially all solid rock. We have between a few inches to maybe a few feet of soil over most of our ridgetops and the road runs right on the crest for the most part. BIL just blasted for his basement and septic on property about 1/4 mi away and had the same geology. He had at most a few feet of topsoil and LOTS of rock to move after the blasting; something on the order of 1000 yds3. I'd offer it to your friend, but unfortunately, it's not much use for building because after it gets exposed to water and freezes a few times it begins to crumble. That's why I characterize it as shale. It is definitely not any type of igneous rock.
 
   / Water line bid #28  
One thing I will say, according to your breakdown, the price of the creek gravel is pretty low. (provided those are tandem loads) I get mostly limestone gravel here and it runs me $235 for a 22 ton load delivered. Creek gravel is a little bit higher here because it has to be hauled in from further away.
 
   / Water line bid #29  
JRobyn,

Dang. That stinketh about the wells. The numbers for the equipment seem in the ballpark for the per hour charge. I don't know what creek gravel is but that is cheap if you are getting 15ish tons per load.

So the only way the bid would be out of whack is the number of hours it takes to do the job. Given the rock they have to go through and the risk that brings to a project.....

Me thinks you are between a rock and hard place.:eek::D

Later,
Dan
 
   / Water line bid
  • Thread Starter
#30  
Maybe between some rock and a wet place (oh, that sounds bad!)
 

Tractor & Equipment Auctions

2018 HINO 258 S/A SERVICE TRUCK (A51243)
2018 HINO 258 S/A...
2025 LandHonor LHR-DFP10 Diesel Fuel Transfer Pump with Hose Reel (A49461)
2025 LandHonor...
3in Poly Pipe (A49461)
3in Poly Pipe (A49461)
2020 CATERPILLAR 326 EXCAVATOR (A51242)
2020 CATERPILLAR...
EVERYTHING SOLD AS-IS WHERE IS!! (A50775)
EVERYTHING SOLD...
2018 FREIGHTLINER CASCADIA TANDEM AXLE SLEEPER (A51222)
2018 FREIGHTLINER...
 
Top