bdw593
Bronze Member
Did the same thing with bout 1000'. Sch 40 in ground sch 80 out of ground. Primed and glued joints, to co-op standards. Had elect inspector ok it before I filled in the trench. Then filled the trench. Then took orange hay twine and sucked it through with a regular shop vac, worked like a charm. Co-op won't use your pull rope, they will use your rope to pull their rope through. They provided all the lubricant etc for pulling wire. In 1000' pull I did not have to install pull boxes. Hope all goes well.. Also got a trick if you get water in the line how to get the rope through.. If you get into that predicament message me....