Fired Road contractor. Build it myself?

   / Fired Road contractor. Build it myself?
  • Thread Starter
#241  
We are getting more stone delivered tomorrow. We have another 90 yds prepared. I was hoping to have a lot more done, but equipment failures, yesterday, cost me about 6 hours of work time.
Working on the ditch.
IMG_5819.JPG

posing up the hill....slowly, slowly
IMG_5818.JPG

My assistant is dutifully shaping the road.


IMG_5815.JPG

It is beginning to take shape.

IMG_5817.JPG
 
   / Fired Road contractor. Build it myself? #242  
I like the quality of your work. You have high standards. How long is the road you are building? If you are like the rest of us tractor nerds, you like the planning and visualization of the project almost as much as the doing. It all adds up to cool stuff, and that leads to more cool stuff and ....
 
   / Fired Road contractor. Build it myself? #243  
This continues to be a great thread.
 
   / Fired Road contractor. Build it myself? #244  
Great progress!!!! Thanks for the update pics. Puts the magnitude of this project into perspective.
 
   / Fired Road contractor. Build it myself? #245  
On the portion that is not ditched yet give a try with the tractor bucket. Approach a right angle to the road and see if it works. It will only take several minutes to try.
 
   / Fired Road contractor. Build it myself?
  • Thread Starter
#246  
On the portion that is not ditched yet give a try with the tractor bucket. Approach a right angle to the road and see if it works. It will only take several minutes to try.

Sometimes it works. There is a lot of rock. I have to break thru it with the excavator. It's really a combination of a lot of different methods we are learning as we go.
 
   / Fired Road contractor. Build it myself?
  • Thread Starter
#247  
I made some more progress today.

This morning IMG_5822.JPG

And then the stone was deliveredIMG_5827.JPG

I had them leave extra so I could tidy things up.

They delivered the culverts that I am going to put in.
IMG_5825.JPG
And I got to work to and dug another 50 yds. Bit by bit we will get it done. All told the piece of road we are building is only 400 yards. But it's hard won yardage.

Eventually, it will be done and done right. The view is getting better all the time
IMG_5834.JPG
 
   / Fired Road contractor. Build it myself? #248  
Looking good so far, great job.
 
   / Fired Road contractor. Build it myself? #249  
The road is looking great! I think you made the right decision by firing your contractor and you get to play with some new toys. I have some road work to do but fortunately its not as extensive as this until we cut several loads of timber.
 
   / Fired Road contractor. Build it myself? #250  
.
One works it as required by the conditions.

You will have a nice looking road when done.
 

Tractor & Equipment Auctions

2017 JOHN DEERE  30G (A50854)
2017 JOHN DEERE...
2022 Continental 16' Enclosed Trailer with ramps (A49461)
2022 Continental...
2018 CATERPILLAR 308E2 CR EXCAVATOR (A50458)
2018 CATERPILLAR...
2017 FREIGHTLINER M2 BOX TRUCK (A51222)
2017 FREIGHTLINER...
2015 VOLVO ECR88D (A50854)
2015 VOLVO ECR88D...
2025 Kivel 48in Forks and Frame Skid Steer Attachment (A50322)
2025 Kivel 48in...
 
Top