Also, it will take many yards of dirt to change the slope of the front face. And if you change it very much you'll start to crowd your pipe inlet.

I have one coupling I didn't use and about 8ft of pipe left to extend if needed. Probably a full day of moving dirt to get the slope where I want it.
 
   / Building Lake Corona #722  
I think if it's an issue to you, go for it. You'll regret not doing it. And you are way too deep into this project to end with regrets!!!! :thumbsup:
 
   / Building Lake Corona #723  
Also, it will take many yards of dirt to change the slope of the front face. And if you change it very much you'll start to crowd your pipe inlet.

Nothing a coupling and short piece of pipe with glue could correct in minutes.
 
   / Building Lake Corona #724  
Nothing a coupling and short piece of pipe with glue could correct in minutes.

Yep. The pipe was secondary. The yardage is the big issue. He'll get it right or he'll keep working at it!!!
 
   / Building Lake Corona #725  
What is your slope now? I think 3 to 1 is as steep as you would want at the waterline and above.
 
   / Building Lake Corona #727  
I have one coupling I didn't use and about 8ft of pipe left to extend if needed. Probably a full day of moving dirt to get the slope where I want it.

Have you gave any thought to getting rye grass planted, while adding finishing touches, too help slow down a heavy rain if one comes along?
hugs, Brandi
 
   / Building Lake Corona #728  
I think if it's an issue to you, go for it. You'll regret not doing it. And you are way too deep into this project to end with regrets!!!! :thumbsup:

EXCELLENT ADVICE !!
 
   / Building Lake Corona
  • Thread Starter
#729  
Yep. The pipe was secondary. The yardage is the big issue. He'll get it right or he'll keep working at it!!!


You are correct. Those extra few degrees adds up to a lot of yards. I'm guessing my slope is currently about 1.5/1. Need to get it to 2/1 at a minimum. Probably puts the bottom around the end of the inlet pipe. Calling for 1/2" to 1" of rain tonight so may be a few days before I get back in to wrap things up.
 
   / Building Lake Corona
  • Thread Starter
#730  
Have you gave any thought to getting rye grass planted, while adding finishing touches, too help slow down a heavy rain if one comes along?
hugs, Brandi

Considering I've been building this on the fly with no real plan I haven't thought about it yet. Figured as soon as I put some down I'd be digging it right back out or tracking all over it.
 

Tractor & Equipment Auctions

CATERPILLAR 336FL EXCAVATOR (A51242)
CATERPILLAR 336FL...
2002 International 4400 SBA 4x2 Flatbed Truck (A49461)
2002 International...
2018 JLG 3246ES 32ft Electric Scissor Lift (A50322)
2018 JLG 3246ES...
72In FEL HD Round Back Bucket (A52128)
72In FEL HD Round...
2016 CATERPILLAR 325FL EXCAVATOR (A51242)
2016 CATERPILLAR...
Land Honor Quick Attach Bale Spear (A50515)
Land Honor Quick...
 
Top