So my five-man crew from the builder showed up this morning... Watching them do the work today, I don't see a viable way to try and pour the slab before the building goes up unless the slab was already there and a building was being put up around it later.
Once the building was squared and the post holes identified, one guy went to work with the auger on a skid steer.
As each hole was finished he moved on and the other four guys would manhandle a 6x6 post into position, square it up, and then dump three bags of cement mix into the holes (the ground was wet, and we had rain in the forecast, so they didn't water the holes, which I found a bit odd).
And then the lightning & rain started around 4pm.. Absent that, they would have probably worked past 7pm to finish most of the framing, since they're from out of town and staying at a local motel overnight.
Tomorrow, they'll be using a 21ft boom attachment on the skidsteer to fly the trusses. With the Skidsteer needing to be along the centerline, had they poured the slab today, that would have been a 1-week delay (if not more) for the slab to cure before they could put that much weight on it.
Trusses assembled:
Boom attachment:
1115: First hole being dug with auger in the back
1330: all holes dug, some posts moved
1430: all posts in place, adding concrete mix and squaring/bracing
1630: Lightning hits... crew starts cleaning up about 10 minutes before the downpour hits