   / House II #121  
Re: House II, Grading

Robert,

I posted the floor plans under the original thread RobS started called "House". But I will be glad to post them on this thread. We found plans we liked on the web and then went about modifying the plans with an architect to make them "unique to us". We took out a porch, added a sun room dropped a bay window and put 2FT on the back of the house and lowered the roof pitches. They were 12/12, but we found 8/12 was more for us (cost and looks).

Okay, I can't find them. But I will see what I can locate and repost them.
 
   / House II #123  
Re: House II, Grading

The siding guys started on Monday, but due to a death in the family they have been off all week. So they may resume tomorrow or Monday.

Other than that the plumbers and heating crews have been working since mid week. The builder has the garage cleaned out so they can pour the floor, they built out some walls in the master bath for the shower and tub unit.

Just got more money from the bank (next interest payment will be big) so the builder is happy. New pics next week, when more siding goes up.

Anyone else building or got any updates on their house projects.
 
   / House II #124  
Re: House II, Grading

Well everyone is back at it this week. The siding crew is in full swing, and they are a great group of guys to talk to as well.

The electricians are at it and they will be done with their rough in work this week. Plumber is going at it and has the waste pipes just about done, but has the hot/cold water lines to install next. So by the end of next week (I hope) all of them and my ADT & premise wiring (Voice, Video, Data & Speaker) wire will be done as well. Buddgets are getting tight.

I will post pics this weekend of the finished siding, since its hard to get good shots in the evening due to lack of sunlight.
 
   / House II
  • Thread Starter
#125  
Re: House II, Grading

Sounds like you're in full swing Michael! We've just finished a major homeowner contribution blitz. We did our own ceramic tile and it looks great. Worked straight through from last Wednesday to Tuesday of this week. 600 square feet of rescrewing the subfloors, laying underlayment, tiling and grouting. Not sure we'll ever do that again, but it was fun and as I said, it looks fantastic.

Now the cabinets are almost all in, hardwood floors are down, interior doors are hung and the finish trim should start today. Only about four more weeks to go /w3tcompact/icons/grin.gif

Yesterday was the first day of school so we both drove our oldest up to the new house to catch the bus. My wife will handle that duty on her own starting today and I'm sure she'll be plenty tired of it all after four weeks. We also change time at the new place (Michigan is on daylight, Indiana is not) so they've got to be up that much earlier. Yes, life is a tad stressful lately.

I did actually see my tractor last night as I put a bucket of tools in the garage. Maybe I'll have a chance to do some mowing or grading this weekend /w3tcompact/icons/smile.gif
 
   / House II #126  
Re: House II, Grading

RobS,

Lets see som pics of the tile. Well the siding guys will finish tomorrow and I will take pics on Saturday of the finished siding. the porch still has to be "finished" with railing, posts, decking etc.

The electrician is done with his rough in tomorrow, the heating guys are done with theirs and the plumber is about done I think as well. I have alarm and in house voice, video, data, and audio being done next week.

So right after the holiday they should be sheet rocking & insulating the walls. The the fun begins.

We expect to move in about 7 weeks so they better get moving or someone is in trouble. The builder is great and he is pressing to finish the other job up as well. But he is very on top of things.

Now for a co-worker who is building. Well her and her boyfriend(?) are building a nice custom home in a nice neighborhood. Well the builder is really ripping them off. I guess he got served with his papers and told them good luck. Not a good attitude. Too bad as he is a big custom home builder.

Oh well it sucks when you are trying to build your dream home and it don't go so well. So far the subs have been great. The siding guys are neat freaks, they clean, clean clean before they leave and they are really nice too.

Lets get some pics.
 
   / House II #127  
Re: House II, Grading

Just when you think things are moving along you get the real view. The siding crew is just about done, but the electricians didn't finish the lighting so they can't finish their work on the porch.

ADT & our VVAD (voice, video, audio, data) guy starts on Tuesday so they my subs are done earlier than planned. But we must wait on the electricians and plumber to get finished. Supposed to move in 7 weeks and I don't see it, but then again who can see the forest for the trees when you are in the middle of it all.
 
   / House II
  • Thread Starter
#128  
Re: House II, Grading

We're less than 4 weeks out now. Can't wait but still a lot to do. I put some fascia boards (cedar) on the porch so the siding guys can finish the soffits there. We ran through 5 gallons of oil based primer and still have over half of the porch boards to prime /w3tcompact/icons/eyes.gif The mason should be back this week to build the piers, then I can go full steam ahead on finishing the porch.

I've got to pick up my VVAD trimouts and work on that soon. Trim guy is hard at work and the electricians have started their trimouts. I stained some wood flooring scraps to finalize our color selection and my wife has the carpet colors all set.

I have some more pictures but couldn't maintain a connection last night. Maybe tonight /w3tcompact/icons/smile.gif
 
   / House II #129  
Re: House II, Grading

I have read this entire post and I have got to say you have done a hell of a job. We are within a week of closing on our new house, but we had a custom builder do almost all of the work. I can't imagine doing all of the projects you have done and still staying married /w3tcompact/icons/grin.gif. Take a look at the web site in my signature to see how our house went up.

Good luck finishing it up!
 
   / House II
  • Thread Starter
#130  
Re: House II, Grading

Wow Brian, your house looks great! Nice web-site. I'm still trying to figure out what to do with all these digital pics of ours when it's all done. I like the way your building project is organized.

Thanks for the compliments. We do have a GC, but have done some things ourselves to add the personal touch. Right now, we're pretty much looking forward to moving in.

Hey, I see you are a fellow Hoosier (at least for now, for me). I also noticed a mention of Boy Scout camp on your web-site. Camp Ransberg by any chance? I spent many a summer there myself with fond memories.

Thanks again for the compliments. Let us know how your move-in goes /w3tcompact/icons/smile.gif
 

Tractor & Equipment Auctions

2004 INTERNATIONAL 4300 CARGO TRUCK (A50854)
2004 INTERNATIONAL...
2008 MAGNUM LIGHT PLANT (A50854)
2008 MAGNUM LIGHT...
2019 FORD F-150 XL SINGLE CAB TRUCK (A51406)
2019 FORD F-150 XL...
2017 Ford F-450 Crew Cab Knapheide Service Truck (A49461)
2017 Ford F-450...
2013 HINO 388 (A50854)
2013 HINO 388 (A50854)
2017 Bad Boy Outlaw XP 61in Zero Turn Mower (A48082)
2017 Bad Boy...
 
Top