How big of a slab could I do by myself?

   / How big of a slab could I do by myself? #151  
When I did my pole barn floor, I left about a foot sticking out beyond the forms to tie the slabs together. That was 9 years ago and it seems to have worked out OK.
View attachment 4201036
That's the same way I did our garage addition... by running the rebar through the form. It helped to keep the rebar in the center of the slab, and I used chairs wired to the underside of the rebar as well throughout the slab.

When I did the adjacent slab, I'd just wire it with that 12-18" overhang in two places so it couldn't shift, and I ran a piece perpendicular across the joints and wired them. It wasn't going anywhere. ;)
 
   / How big of a slab could I do by myself? #152  
See post #62 in this thread. šŸ™ƒ


First slab ready to pour...
(click to enlarge)
IMG_7365.jpeg

Second slab ready to pour...
(click to enlarge)
You can see the rebar for the 1st slab tied to the 2nd slab.
I used 2x6 so the concrete is about 5-5.5" thick.

IMG_7366.jpeg
 
   / How big of a slab could I do by myself? #153  
Eddie (and Paul) -
Great!
Two questions - How do you tie in the separate pads? (or do you?) And if you just lay rebar sticking out, how much length do you run for overlap?
There are two opposite opinions; 1) tie them together with rebar dowels, maybe bonding agent, or a "key way" joint.(structural slabs are like this)
Option 2), dont bond them at all, actually put expansion joint between them, and allow them all to float separately (sidewalk and driveways are normally like this)

For me, I have kinda gone back and forth on to tie or not; but I have settled on my slabs, im going to do an expansion joint between them, and then run a poly bulalyne(sp?) caulk sealer over the expansion joint.
 
   / How big of a slab could I do by myself? #154  
So, as a rough guideline, with exceptions, if it has a footer, you really should avoid cold joints, and have a way to bond the slabs together, rebar, epoxy dowels, key ways, ect

Generic, no footer, not taking point loads, expansion joint and no structural connection (sidewalks, driveways, pool barn floors, ect)

To construct a Keyway joint, you nail a 1x2 or 2x2 on the form boards of pour one, creating a socket, bell, or grove when the form is stripped. Then the 2nd pour creates the spigot, tennon, tongue; locking them together. Additionally, the cold/cured concrete can be coated with a bonding agent. The rebar dowels left flying (as shown) work, as does a flat face, and drill and epoxy dowels in prior to the 2nd pour.
 
   / How big of a slab could I do by myself? #156  
Generally sidewalk, driveways, and non load bearing slabs are kinda treated as non structural, and they typically use an expansion joint between pours.
Screenshot_20251008_160527_Google.jpg
 
   / How big of a slab could I do by myself? #157  
See post #62 in this thread. šŸ™ƒ


First slab ready to pour...
(click to enlarge)
View attachment 4204377

Second slab ready to pour...
(click to enlarge)
You can see the rebar for the 1st slab tied to the 2nd slab.
I used 2x6 so the concrete is about 5-5.5" thick.

View attachment 4204379
If you look at picture one above, I had to drill and epoxy pins into the existing garage foundation so the new slab(s) would be tied to the old slab and wouldn't move around. I tied the pins to the rebar in the new slab(s).
 
   / How big of a slab could I do by myself? #158  
The argument against dowels, lets say my approach slab, if the slab settles, its either going to simply settle maybe 3/4" and thats it, with no dowels, or crack, and break, but still settle the same with dowels.
If I was doing a full rebar mat, with bends at the right points, and tied to dowels, yes, you could effectively bridge the settled material, but its not really the same as throwing rebar in. The rebar is strategically placed to counter act specific load points, some place towards the top of the concrete, and in other places towards the bottom, to take the tension in the "beam".

Not to nerd out too much about loads and beams
 
Last edited:
   / How big of a slab could I do by myself? #159  
The argument against dowels, lets say my approach slab, if the slab settles, its either going to simply settle maybe 3/4" and thats it, with no dowels, or crack, and break, but still settle the same with dowels.
That's why I put 4' deep 12" sonotube down every 8' along the outside edges and between slabs, in addition to the pins in the existing slab, and in addition to the 12" deep by 12" wide footing all the way around. It's not going anywhere, ever. šŸ™ƒ
 
   / How big of a slab could I do by myself? #160  
If I don’t tie the expansive soil causes shifting…

For small sidewalks I use roto-hammer with 20 penny nails.

For slabs it’s extending the 1/2 inch rebar into the new pour 18ā€ or longer if the rebar runs wild.
 

Tractor & Equipment Auctions

2014 Ford F-150 Ext. Cab Pickup Truck (A55788)
2014 Ford F-150...
New Holland TS 75 Front Loader Utility Tractor (A53421)
New Holland TS 75...
(4) 16" 8 LUG RIMS (A54756)
(4) 16" 8 LUG RIMS...
Hydraulic Concrete Mixer Skid Steer Attachment (A55787)
Hydraulic Concrete...
More info coming soon! (A55787)
More info coming...
Year: 2019 Make: Chevrolet Model: Silverado LD Vehicle Type: Pickup Truck Mileage: 83515 Plate: B... (A55852)
Year: 2019 Make...
 
Top