LarryRB
Guest
this coming spring I will do underground electric for the sister in law.. I already got the permit from the electric company.. Here, on the Ma/Ct state lines, 4" schedule 40 is required for any run 200 ft or longer, and at 42" down minimum.. Anything less, only causes aggravation later. I do a lot of trenching for underground electric and never once saw anything below the sch40/4,even on very short runs,,,