How do you guys usually cut the bench? It seems like you would need an excavator digging so you wouldn't push the whole hill over at once and you could compact in lifts. I just did a job like this with my backhoe on a steep slope and my butt was puckered the whole time.
I can see already where I'll have to get long winded again but, any way you do it, it should be stripped of topsoil and pucker factor is a big part of that Job!
I would guess that any trail or driveway would require no more than 2 bench cuts. The second one would be your finished subgrade and should provide enough fill bring the lower one up to that grade, as you can always cut further into the backslope for more fill if necessary.
Something you absolutely must consider is drainage as a torrential downpour can take out hours of work in minutes. Been there done that more than once. Worst one lost a slope 10-12 ft deep 40-50 ft long
Basically with excavator, dig out up hill side and place on slope ahead of you to make a path ahead of your downhill track to level yourself and keep on digging. When on next bench up, spread on lower bench to bring up in layers for compacting.
With dozer, hook out an area with blade corner (or up and down the slope if not too steep) to level a starting pad then just keep working that grade through the hillside, hook it out and push it over. Tilt and angle blades help greatly. Gravity helps going downhill but I preferred to work uphill when possible where really steep, it's harder pushing but you're less likely to get in trouble. You can always back downhill but not always uphill. When we were filling the lower bench from the next step up, we usually worked 2 dozers. Big top one pushing over and smaller lower spreading the material for compaction. Many times we had to add material especially when doing embankments to flatten slopes.
Grade tolerances are quite lax when benching as the idea is to get a basically level subgrade for the fill to sit on to prevent slides.
Hope this helps
And Rio,
300 yards seems like great production for a skid steer but don't get over that edge when it gets steep. An excavator can get out of trouble by pushing itself out and dozers can generally do more than you've got pucker for, but skidsteers can hit a soft spot or something and get away in a hurry as I'm sure you're aware.