circlelake said:Could a person run a level string across one end and follow that by lowering and lifting the box blade? Or possibly a laser light of some type one that spins like brick layers use. Just throwing out some thoughts as I've got to tackle the problem in the next couple years.
Get a lock level, a measuring stick, and a fixed stick.
set your lock level up on your fixed stick ( shovel handle, with shovel planted in the ground ). Plant this off the 'pad' area that you are leveling. Now, establish what grade you want to fill or cut to by using a 2nd shovel to either build a flat top pad, or cut a depression. Pad or depression only needs to be about a shovel with wide on the sides. Put your measure stick on that pad / depression, and have someone look thru the lock level and see what the measurement is. Now.. go to other areas and cut depressions or make pads, and build up or cut down till the person looking thru the lock level see's the same number as before.. Congratulations.. you just shot grade.
Now.. you have a building pad or excavation site that has markers on it that you can cut or fill to. The raised pads or cut depresions will be grade markers. You can stick fancy 'flags' in them to mark them, or just cut some flags from sapling branches to help make them visible.
This is haow many road contractors did it before lasers were commonly used... I've walked many hundreds of miles of subgrade and finish grade doing it this way.