SPIKER
Elite Member
hi Av8ter:
thanks for the input:
today I was looking again at the barn setup. right now the biggest problem is where to put the pit in the barn. the barn is 36' wide and has posts on 10' ctrs down the middle. the 9' door is centered on the left side. I don't have any way of digging the dirt using my tractor mounted back hoe and then getting the dirt into a dump to get out side. as the back hoe does not swing around to the side far enough to dump into the trailer. that means putting the pit sideways in the barn for easy dumping and that will also let the barn still to be used for storage in the mean time while the floor work is going on. (I ordered all the infloor radiant stuff yesterday form tek supply http:www.tek-supply.com ) almost 3 grand for the infloor tube fittings and bubble foil / moisture barrier stuff but I ordered enough to do the 10 lean too and the extra for a 2nd project.)
anyhow I'm thinking it will be the easiest way and when I start the pit and footers, I'm going to pour them as well as footers for "I" beams so I can remove one center 6x6 post and replace it with a beam set between the remaining posts and NEW footers I'll pour. (have to support the 2nd floor with jacks while the 6x6 is removed and the steel I beam installed.) not a problem and then the access for the pit would be much easier.
the last resourt is a new small additional 2 car garage outside increase the roof height on one bay for lift. cost wise I would end up in the 10K range that way by the time I add building & lift if not more. so that means I could farm out the pit install for about the same price....
ok nuf thinking. too late for that.
Mark /forums/images/graemlins/ooo.gif
thanks for the input:
today I was looking again at the barn setup. right now the biggest problem is where to put the pit in the barn. the barn is 36' wide and has posts on 10' ctrs down the middle. the 9' door is centered on the left side. I don't have any way of digging the dirt using my tractor mounted back hoe and then getting the dirt into a dump to get out side. as the back hoe does not swing around to the side far enough to dump into the trailer. that means putting the pit sideways in the barn for easy dumping and that will also let the barn still to be used for storage in the mean time while the floor work is going on. (I ordered all the infloor radiant stuff yesterday form tek supply http:www.tek-supply.com ) almost 3 grand for the infloor tube fittings and bubble foil / moisture barrier stuff but I ordered enough to do the 10 lean too and the extra for a 2nd project.)
anyhow I'm thinking it will be the easiest way and when I start the pit and footers, I'm going to pour them as well as footers for "I" beams so I can remove one center 6x6 post and replace it with a beam set between the remaining posts and NEW footers I'll pour. (have to support the 2nd floor with jacks while the 6x6 is removed and the steel I beam installed.) not a problem and then the access for the pit would be much easier.
the last resourt is a new small additional 2 car garage outside increase the roof height on one bay for lift. cost wise I would end up in the 10K range that way by the time I add building & lift if not more. so that means I could farm out the pit install for about the same price....
ok nuf thinking. too late for that.
Mark /forums/images/graemlins/ooo.gif