Pole building question

   / Pole building question #1  

Newtocvt

Bronze Member
Joined
Apr 11, 2017
Messages
97
Location
Menomonie,Wisconsin
Tractor
New holland 54d
I am thinking of building a pole building for general storage. Mostly for implements I don't want to leave out all winter. I don't need an insulated or heated building and was thinking about just gravel floor. Size wise I was thinking about 24x32 with one 9 foot garage door and a service door. No windows. The area I am thinking about slopes 2-3 feet over the 32' span. My question is can I set the post before the site is leveled and graded. My theory is I can set the post 4 feet deep with my post hole digger than the back full and gravel would essentially make the 6-7 feet deep. Any thoughts?
 
   / Pole building question #2  
I am thinking of building a pole building for general storage. Mostly for implements I don't want to leave out all winter. I don't need an insulated or heated building and was thinking about just gravel floor. Size wise I was thinking about 24x32 with one 9 foot garage door and a service door. No windows. The area I am thinking about slopes 2-3 feet over the 32' span. My question is can I set the post before the site is leveled and graded. My theory is I can set the post 4 feet deep with my post hole digger than the back full and gravel would essentially make the 6-7 feet deep. Any thoughts?


I think you will find it to be more than a major nuisance to be grading around posts already set.
 
   / Pole building question #3  
That. Even if it means you build a retaining wall.
Jim
 
   / Pole building question #4  
And do have a bldg code? Around here you'd need to have a footing under each post, inspected before backfill. Not a bad idea, even for storage.
Jim
 
   / Pole building question
  • Thread Starter
#6  
No building code here. I already checked with the township only thing they care about is the road setbacks. It sounds like I should just get the area prepared first.
 
   / Pole building question #7  
Prior proper preparation prevents poor performance.
 
   / Pole building question #8  
Couple of things we had a high lift level our pad and really compact it so it shouldn't settle. Second if you do metal I highly recommend insulating the roof or it is going to sweat and drop water on your implements, the bumble wrap to do my 30x40 was an extra 300$ well worth it. I would level, compact then set your posts
 
   / Pole building question #9  
I had a couple feet of fill added for my pole shed and had a driveable vibratory roller go aver it a couple times. When I had to dig for some plumbing pipes I had a difficult time shoveling and picking through it. That is a good thing and money well spent.
 

Tractor & Equipment Auctions

Cultipacker (A47809)
Cultipacker (A47809)
2018 Toyota 8FGCU32 Forklift  Reliable Performance with Low Hours! (A46878)
2018 Toyota...
JCB 270T (A46443)
JCB 270T (A46443)
TPM 20K Mini Excavator (A47809)
TPM 20K Mini...
TOFT 680 Hyd Hammer (A47809)
TOFT 680 Hyd...
2011 BIG TEX TRASH TRAILER (A47001)
2011 BIG TEX TRASH...
 
Top