Newtocvt
Bronze Member
I am thinking of building a pole building for general storage. Mostly for implements I don't want to leave out all winter. I don't need an insulated or heated building and was thinking about just gravel floor. Size wise I was thinking about 24x32 with one 9 foot garage door and a service door. No windows. The area I am thinking about slopes 2-3 feet over the 32' span. My question is can I set the post before the site is leveled and graded. My theory is I can set the post 4 feet deep with my post hole digger than the back full and gravel would essentially make the 6-7 feet deep. Any thoughts?