5030tinkerer
Gold Member
I have a septic tank with an additional perhaps 500 gallon poly tank downstream of it that houses a sump pump whose job it is to pump the water out to a leaching field. When the pump failed last week, I noted that the old pump's float was set to come on after only a few inches of water existed in the tank. Trying to limit the number of times that the new pump has to kick on, I set the new float switch with the new pump so that the tank fills about half full before the pump will kick on. By so doing, however, I am now realizing that I am asking my leaching field consisting of 4 or 5 100' runs to accept a pretty large quantity of water all at once. While it is true that the field has more time to dry back out between each influx of water, am I asking for trouble by setting my float switch this way?