Heat and water system. I dug a well at the same time we put in the frost walls and hit water at 8 feet and dug a total of 12, back filled the tiles with all the stone I screened out of my back fill. Pumped it out several times and got well over 1000 gallons.
Pit lid is all done, 2x2x1/4 inch square tube and 1/4 inch plate.
more photos to come when the walls are all done in a week or so.
Pit lid is all done, 2x2x1/4 inch square tube and 1/4 inch plate.
more photos to come when the walls are all done in a week or so.