tommu56
Elite Member
Aaron,
They are side by side and fed thru only one meter.
The "InterLockkit" lockout are not code approved i my jurisdiction since they are not UL approved. Read their fine print and they say "Tested to UL standard" but they are not UL approved. That's why I plan to have those new panels with the interlocks built in installed.
Thanks, Tim
On a note UL testing is done to the manufacturers spec's.
Not to a standard set by an government agency.
so mfgr set's the spec and UL tests to this spec to see if it complies.
tested to UL standard means
mfgr set spec and a different lab tested it to this spec to see if it complies not the UL lab.
most electrical inspectors don't even know the testing procedures
tom