Well I've been saving for almost a year, and I've finally booked this for a week at the end of jun/ start of july!
Mine just won't have the tooth bar, and I believe it's got an 84" bucket, but I'll have to check.
So, some numbers to throw out there; 10km/hr max speed, 21 cubic foot bucket, .5km gravel pile to house, .5km trail length. So the average trip will be .75km, or 1.5km round trip. 9min or roughly 6 trips per hour... let's round down to 5. 5 trips per hour times 40 hours (other work to do that should take a day)= 200 trips X 21 cubic feet= 4200 cubic feet or 155.5 yards or around 10 tandem loads.
I'll be smoothing trail as I go, so should be able to travel at a good speed, although maybe not full speed, and I'll be compacting as I go too. I asked if they had a bigger bucket, but they don't. What are your thoughts of me getting some 6X1/4" flat bar and tacking that around the bucket so it holds more/ trip? Then just grind off before bringing back?