My father started this entryway about 3 years ago with future plans on adding a gate down the road. He said he wants to tighten up security. Since I have free time at the moment (between new job) we decided to finish the project. This entryway will have 6 foot pillars next to the drive with a sloping wall that slopes down and curves to a smaller 4 foot pillar on the ends. He wants 2 automatic gates with a keypad/intercom that is tied to the phone so when someone pulls up and doesn't know the code or have a wireless transmitter, the call button rings the house phone and a command can be given to open up the gate. The openers will probably be from Chamberlain but definitely not a Mighty Mule.
The pillars and curved wall will be sitting on a 26" deep reinforced footer and will be made of block then brick faced. I have laid blocks before but we will end up subbing out the brick work as that is something we have never done before. I have talked to a few masonry guys and will place the brick ties in the block wall as per their recommendations.

This is the entry area. The road is about 25 yards behind where the picture was taken. The intercom will be to the left. The 2 steel I-beams are 4 foot in the ground with concrete and will be 6 foot above the footer. We will build the pillar around this and will attach the gate (weld the hinges) to this. The gates shouldn't sag at all!
IMAG0301 (Medium).jpg

This is leaving the property. The blocks we plan to use are stacked on the right.
IMAG0303 (Medium).jpg

The footing was dug by hand. Man it would have been nice to have a mini excavator! The first footing was down hill so in order to make both sides level with each other, we had to add forms and backfill. The other footer was higher up so we will use the earth as a form. We placed rebar every 14" and tied everything together and added wire to fill in the gaps as we didn't want to spend a fortune on rebar.
IMAG0293 (Medium).jpg
IMAG0295 (Medium).jpg
IMAG0292 (Medium).jpg
IMAG0296 (Medium).jpg
IMAG0291 (Medium).jpg

We were all ready to order concrete for Tuesday when the sky let out 3" of rain yesterday. We had to pump out the "trenches" and will have to fix the form in one spot where the rain washed out the dirt backfill.
IMAG0297 (Medium).jpg
IMAG0298 (Medium).jpg
IMAG0299 (Medium).jpg

We're not suppose to have rain for the next 7 days so we will let it dry out more and pour the footing on Wednesday. We will also place rebar into the concrete to tie the block wall to the footer. We will probably add rebar every 3 feet and fill that blocks cavity for strength.

More to come later.

Doug
 

Attachments

  • IMAG0294 (Medium).jpg
    IMAG0294 (Medium).jpg
    103.4 KB · Views: 404
/ Entryway/Gate project
  • Thread Starter
#2  
Poured the concrete today and placed rebar to tie the wall in and it took 9 yards. Glad I didn't have to mix all 450 bags. (We got a truck)

IMAG0304 (Medium).jpg
IMAG0305 (Medium).jpg
IMAG0306 (Medium).jpg

Tomorrow we are getting ready for another 11 yards for the low-water bridge down by the creek. We bought corral panels that are 4' x 15' and the wire is as thick as a pencil, to reinforce the concrete. We used the extra yard of concrete today to reinforce the rocks and culvert that is in the creek. We are trying to get this done before the AG equipment comes to plant beans. I'll post pictures of tomorrows progress.
 
Last edited:
/ Entryway/Gate project
  • Thread Starter
#3  
We got the coral panels all wired up and will pour 10 yards of concrete on Friday. We used rocks as spacers to keep the panels about midway in the concrete. We are going to use concrete come-alongs to pull the concrete into place. We won't float the pad as it will only be for equipment to access the other field. The only thing we need to worry about is that there are no low spots that hold water. The cross-over is 30' X 22' X 5"

IMAG0308Medium.jpg


IMAG0307Medium.jpg
 
/ Entryway/Gate project #4  
Thanks for the pictures
 
/ Entryway/Gate project
  • Thread Starter
#5  
It doesn't seem like anyone is interested in this project by the looks of the replies so I guess this will be my last update.
 
/ Entryway/Gate project #6  
Hey now, that's a bit rash!

I think most of us appreciate the pictures and descriptions, even if there's not a whole lot to comment on. There's always more comments once you finish a project, too.

Nice job on those curved forms.
 
/ Entryway/Gate project
  • Thread Starter
#7  
Thanks Deezler. I'll keep posting my progress then if there's an interest. Tomorrow I get the lovely task of pouring and spreading 11 yards of concrete at the low-water crossing. I started a dry run of blocks for the entry way so I'll post pictures later tonight.
 
/ Entryway/Gate project #8  
First time I've seen this thread. That looks like one seriously substantial gate! Are you trying to keep someone out or....in? haha
 
/ Entryway/Gate project
  • Thread Starter
#9  
First time I've seen this thread. That looks like one seriously substantial gate! Are you trying to keep someone out or....in? haha

It's a project that's been on the back burner for a few years and since I'm in between jobs it's a good time to get started. It will increase the value of the house while tightening security.
 
/ Entryway/Gate project #10  
I am looking to make a security gate so please keep the pictures coming.
 
/ Entryway/Gate project #11  
Looks like a good project-I'm planning on putting up a cedar log ranch style gate this summer after fininshing an inside project for my Bride. Seeing your project akes me want to get outs even more.

What is the size of each of the gate sections? I may have missed it, but didn't see it.

Also, I'm wondering about the low water crossing. Did I understand that you will pour it, then drag it into position? If so, was there a reason not to pour it in place?

Good luck with the weather here in Kansas!
 
/ Entryway/Gate project
  • Thread Starter
#12  
The opening between the beams is 14 feet so we will have two 7 foot gates. The low water crossing will be poured in place on top of a 20" culvert that is already installed. We have big rocks that were put about 5 years ago (some 100-150 pounds) but this creek floods out during heavy rains washes everything down. We're hoping this will be a permanent fix so the farm equipment can pass between fields without having to bring in a big excavator to fix the area.

Here is the dry-run of the blocks to give you a better picture of what it will look like and the brick face in the last picture.

IMAG0309Medium.jpg


IMAG0312Medium.jpg
 
/ Entryway/Gate project #13  
I'm interested. Took a lot of pictures of different gates & entrances a few years ago while traveling. Had plans to build one but ended up selling the property. It's still on the list for my current place but in the meantime I stuck a couple of logs in and hung gates on them.

Joe H
 
/ Entryway/Gate project
  • Thread Starter
#14  
We poured the low-water crossing first thing this morning to beat the rain that is expected tomorrow afternoon and the AG equipment that's going to plant the beans later next week. It took 11 yards and it turned out great. We didn't finish the surface because leaving it rough should help with traction if it gets wet and the place it's located isn't visible unless you're down by the creek. We spaced the coral panels up on rocks to keep it centered in the pour and that worked out great as there is no way to pull the heavy panels up while you're pouring and standing on them. We kept the thickness to about 5" with the sides getting about 10".

Next week I'll start setting the entryway blocks.


We poured more concrete on the bank sides to help keep the water in the center and to keep it from washing out the sides.
IMAG0313Medium.jpg

IMAG0314Medium.jpg

IMAG0316Medium.jpg


This is the down stream side that slopes to the upstream side so water will drain off.
IMAG0317Medium.jpg


This is the upstream side where the culvert is located. We put our names in the smoothed out area on the left.
IMAG0318Medium.jpg
 
/ Entryway/Gate project #15  
I am following as well, just one comment. You blew your security by adding your names to the concrete, now everyone knows who lives there:laughing:
 
/ Entryway/Gate project #16  
I am following as well, just one comment. You blew your security by adding your names to the concrete, now everyone knows who lives there:laughing:
:thumbsup:He's fine he spelled them wrong for extra protection! :D
 
/ Entryway/Gate project #17  
There is a serious amount of yards of concrete involved here.
I am impressed with the work you are doing. Please keep the updates coming as I am designing an gate entry as well.
 
/ Entryway/Gate project
  • Thread Starter
#18  
I took a few days off to do other jobs around the house/farm and started back on the entryway. Today I set two courses of block on the east wall. I'm not an expert at laying block...let alone a curved wall. My expertise in laying blocks came form the Army and we really had to do was straight walls so this is a learning experience for me. All I'm doing is building the backbone for when the real professional comes to set the bricks. All I need to worry about is keeping everything level and plumb!

I cut a channel in the first block and inserted a piece of conduit to let out any water if it rains. I didn't want a large pond in here. If there's a chance for rain, we'll cover the other holes with blocks. I also put conduit in the far pillar so we can add a lamp on the top. After setting the first course we added the brick ties in the mortar joints. This will hold the brick facia to the wall.

IMAG0327Medium.jpg


IMAG0328Medium.jpg


Normally a string line is used as a guide to keep the courses level but that won't work with a curved wall so we had to really pay attention and keep everything level with a 4' level. I was able to set the first block on the far pad with a line level before we started the second course. We will use that block to lay the first course on that side then use a line level off of the second course to keep both sides the same.

IMAG0330Medium.jpg


IMAG0331Medium.jpg


I'm not in a big hurry to finish this but I do hope to work on it every day. My goal is to do on course/day so the mortar is good and dry and I don't kill myself.
 
/ Entryway/Gate project #20  
Dishpointer said:
My father started this entryway about 3 years ago with future plans on adding a gate down the road. He said he wants to tighten up security. Since I have free time at the moment (between new job) we decided to finish the project. This entryway will have 6 foot pillars next to the drive with a sloping wall that slopes down and curves to a smaller 4 foot pillar on the ends. He wants 2 automatic gates with a keypad/intercom that is tied to the phone so when someone pulls up and doesn't know the code or have a wireless transmitter, the call button rings the house phone and a command can be given to open up the gate. The openers will probably be from Chamberlain but definitely not a Mighty Mule.
The pillars and curved wall will be sitting on a 26" deep reinforced footer and will be made of block then brick faced. I have laid blocks before but we will end up subbing out the brick work as that is something we have never done before. I have talked to a few masonry guys and will place the brick ties in the block wall as per their recommendations.

This is the entry area. The road is about 25 yards behind where the picture was taken. The intercom will be to the left. The 2 steel I-beams are 4 foot in the ground with concrete and will be 6 foot above the footer. We will build the pillar around this and will attach the gate (weld the hinges) to this. The gates shouldn't sag at all!
<img src="http://www.tractorbynet.com/forums/attachment.php?attachmentid=264187"/>

This is leaving the property. The blocks we plan to use are stacked on the right.
<img src="http://www.tractorbynet.com/forums/attachment.php?attachmentid=264188"/>

The footing was dug by hand. Man it would have been nice to have a mini excavator! The first footing was down hill so in order to make both sides level with each other, we had to add forms and backfill. The other footer was higher up so we will use the earth as a form. We placed rebar every 14" and tied everything together and added wire to fill in the gaps as we didn't want to spend a fortune on rebar.
<img src="http://www.tractorbynet.com/forums/attachment.php?attachmentid=264192"/>
<img src="http://www.tractorbynet.com/forums/attachment.php?attachmentid=264194"/>
<img src="http://www.tractorbynet.com/forums/attachment.php?attachmentid=264190"/>
<img src="http://www.tractorbynet.com/forums/attachment.php?attachmentid=264195"/>
<img src="http://www.tractorbynet.com/forums/attachment.php?attachmentid=264189"/>

We were all ready to order concrete for Tuesday when the sky let out 3" of rain yesterday. We had to pump out the "trenches" and will have to fix the form in one spot where the rain washed out the dirt backfill.
<img src="http://www.tractorbynet.com/forums/attachment.php?attachmentid=264196"/>
<img src="http://www.tractorbynet.com/forums/attachment.php?attachmentid=264197"/>
<img src="http://www.tractorbynet.com/forums/attachment.php?attachmentid=264198"/>

We're not suppose to have rain for the next 7 days so we will let it dry out more and pour the footing on Wednesday. We will also place rebar into the concrete to tie the block wall to the footer. We will probably add rebar every 3 feet and fill that blocks cavity for strength.

More to come later.

Doug

I see you found a way to make that Deere drivable... Ha ha, couldn't resist. Project looks great!
 

Marketplace Items

Giyi DHC Mini Quick Attach Forks (A60463)
Giyi DHC Mini...
DRAGON 500 BBL ACID TANK (A58214)
DRAGON 500 BBL...
ROSCO SPR-H CHIP SPREADER (A59823)
ROSCO SPR-H CHIP...
2019 Chevrolet Silverado 1500 Pickup Truck (A55973)
2019 Chevrolet...
2009 Kubota M108S (A60462)
2009 Kubota M108S...
2018 GENIE GTH-5519 TELESCOPIC FORKLIFT (A59823)
2018 GENIE...
 
Top