westcliffe01
Veteran Member
Gravel bed under floor and around foundation perimeter. Both with a clear and downhill slope to the sump, add 1 sump pump and you will have no issues. Of course you will need to landscape so that surface water rolls away from the foundation and not towards it. Settlement after backfill is a common problem that funnels surface water right to the basement wall. Add gutters that do not extend away from the house and you have a recipe for disaster.
How to handle the landscaping if the area is truly flat is always a major question. One approach is to elevate the ground floor a few feet and bring in enough dirt to accomplish a nice gradual slope all around the building. In your case you may not have to bring in dirt since you are going to make a big dirt pile excavating for the basement in the first place.
At the company where I work, the grounds are quite extensive. But it is right next to a small lake, and if you dig down 6 ft you have a swimming pool by the next day. The company decided to put in a 10 million extension with new test facilities, one of which was a big 4wd rolling road dynamometer. The rolls themselves were possibly 4 or 5 ft in diameter and that + the foundations and the motor/alternators that drive or brake the rolls all had to be housed underground in the basement. Some big excavators arrived and dug the big hole. It didn't take long at all.. The next day the hole had 2-3ft of standing water in it. Since there was no better place to put the facility, plan B kicked in. A well driller was hired and sank several 8" wells throughout the construction site. The wells were hooked up and all the plumbing combined to about a 6" diameter steel pipe that was run to a pond a few hundred yards away which is part of a natural drain. Those wells then ran 24/7 for the next 3 months and artificially lowered the ground water in the construction zone to a depth well below that needed for construction.
The contractor came back on site, completed the drainage, gravel bed and poured the foundation, walls and slab. The gravel bed fed several large sump pumps, and now that construction is complete, there is a continual stream from the sump discharge which is holding the water down. Since the height that the water has to be raised is not very high and it discharges to atmosphere, the cost of running the sump pumps is very small compared to operating the $10 million test building. So everyone got what they wanted, except for the 3 month delay to lower the water table in the first place.
Now I should add that the soil in the area of this facility is all glacial deposit sand and gravel, which accounts for the free passage of the water. Eddie, if you have deep clay, the flow of water through the clay will be very slow. If you dig down and reach a gravel layer, then I would for sure give it some time to see if it is active as the path for groundwater flow because that is an altogether different task for a home owner than merely providing drainage and a sump pump.
How to handle the landscaping if the area is truly flat is always a major question. One approach is to elevate the ground floor a few feet and bring in enough dirt to accomplish a nice gradual slope all around the building. In your case you may not have to bring in dirt since you are going to make a big dirt pile excavating for the basement in the first place.
At the company where I work, the grounds are quite extensive. But it is right next to a small lake, and if you dig down 6 ft you have a swimming pool by the next day. The company decided to put in a 10 million extension with new test facilities, one of which was a big 4wd rolling road dynamometer. The rolls themselves were possibly 4 or 5 ft in diameter and that + the foundations and the motor/alternators that drive or brake the rolls all had to be housed underground in the basement. Some big excavators arrived and dug the big hole. It didn't take long at all.. The next day the hole had 2-3ft of standing water in it. Since there was no better place to put the facility, plan B kicked in. A well driller was hired and sank several 8" wells throughout the construction site. The wells were hooked up and all the plumbing combined to about a 6" diameter steel pipe that was run to a pond a few hundred yards away which is part of a natural drain. Those wells then ran 24/7 for the next 3 months and artificially lowered the ground water in the construction zone to a depth well below that needed for construction.
The contractor came back on site, completed the drainage, gravel bed and poured the foundation, walls and slab. The gravel bed fed several large sump pumps, and now that construction is complete, there is a continual stream from the sump discharge which is holding the water down. Since the height that the water has to be raised is not very high and it discharges to atmosphere, the cost of running the sump pumps is very small compared to operating the $10 million test building. So everyone got what they wanted, except for the 3 month delay to lower the water table in the first place.
Now I should add that the soil in the area of this facility is all glacial deposit sand and gravel, which accounts for the free passage of the water. Eddie, if you have deep clay, the flow of water through the clay will be very slow. If you dig down and reach a gravel layer, then I would for sure give it some time to see if it is active as the path for groundwater flow because that is an altogether different task for a home owner than merely providing drainage and a sump pump.