4 years ago I swore I would never do this again. This was prob my least favorite job during the last build. Hoping to get all of the t&g sanded and stained this weekend for the outside porches.

All of the equipment is lined up for Monday. Two scissor lifts, forklift, telehandler, my tractor and forks, and crane on wednesday.

2018-01-04_07-53-38
 
   / Timber Frame Build - Round 2 #162  
T-minus 10 days and the cloud should be lifted, lol. Hard to believe our install date is almost here already. Here's a couple pics of our bar top. Getting it through a 12 ft door was challenging. Also a huge difference today with our foam installed. No problems keeping things warmed up inside now. That was a lot of surface area without insulation.

20171229_123224

20171229_123057

Is that one slab? Or is it sections end to end. That looks huge. Jon
 
   / Timber Frame Build - Round 2
  • Thread Starter
#163  
Is that one slab? Or is it sections end to end. That looks huge. Jon

It is one slab. 32-34" wide and 18-20ft long. Can't quite remember exact length. We will probably cut down to about 15 ft I'm guessing. I'll start framing up the bar area once the timber install is finished.
 
   / Timber Frame Build - Round 2 #164  
It is one slab. 32-34" wide and 18-20ft long. Can't quite remember exact length. We will probably cut down to about 15 ft I'm guessing. I'll start framing up the bar area once the timber install is finished.

How do you plan to keep it from cracking? Or is it kilned dry? Jon
 
   / Timber Frame Build - Round 2
  • Thread Starter
#165  
How do you plan to keep it from cracking? Or is it kilned dry? Jon

It is kiln dried already. Any checks that would develop along with a few of the open knot holes will get resin filled.
 
   / Timber Frame Build - Round 2 #166  
It is kiln dried already. Any checks that would develop along with a few of the open knot holes will get resin filled.

Looking forward to the finish top. I sure enjoy these projects threads. Jon
 
   / Timber Frame Build - Round 2
  • Thread Starter
#167  
Got the overhead door removed this evening and temporary doors up to block the opening. Ended up using some scrap lumber, scrap insulation, and shrink wrap to make a couple of 12'x 6' doors to keep the heat in. Everything is cleared out and cleaned up ready for timbers. Should arrive around 9am tomorrow morning.

2018-01-07_08-24-45
 
   / Timber Frame Build - Round 2 #170  
That's exciting!!!! This is gonna be an interesting week!!!
 
   / Timber Frame Build - Round 2 #172  
Thats cool. Can't wait to see it.
 
   / Timber Frame Build - Round 2
  • Thread Starter
#173  
The crew made some great progress today. Both lower wings are complete. Tomorrow is going to be interesting watching how they do the vaulted ceiling. Because to they have a roof overhead and no crane to lift with they designed the frame different then normal. Usually they would build the center section as a bent and raise the entire section at once. Weather was also great today. Topped out at 50 degrees. I picked up my post plates and risers today and was able to do my painting outside. We had a low of -14 just 8 days ago.

DSC_6796

DSC_6789

DSC_6780


DSC_6787
 
   / Timber Frame Build - Round 2 #174  
Since it's all decorative and not supporting any load, why did you go with posts?
 
   / Timber Frame Build - Round 2
  • Thread Starter
#175  
Since it's all decorative and not supporting any load, why did you go with posts?

Are you talking about the interior posts that sit in the middle of the floor? If so they are supportive of the vaulted ceiling. Center portion is going well so far today. They built the entire center portion on the ground then used the forklift to set.

DSC_6807

DSC_6804

DSC_6809
 
   / Timber Frame Build - Round 2 #176  
:thumbsup: VERY COOL!!!
 
   / Timber Frame Build - Round 2 #177  
Looking great, love it.
 
   / Timber Frame Build - Round 2
  • Thread Starter
#179  
Last section going up then ready to start prep for tomorrows outside install.

2018-01-09_01-32-01
 
   / Timber Frame Build - Round 2 #180  
Last section going up then ready to start prep for tomorrows outside install.

2018-01-09_01-32-01

What are the plans for the tops of the timbers? Some kind of covering to hide building insulation? Or will lighting effects hide it? Jon
 

Tractor & Equipment Auctions

JOHN DEERE 7230R TRACTOR (A60430)
JOHN DEERE 7230R...
KBH Tender (A56438)
KBH Tender (A56438)
SANY SY225C 9C5KL EXCAVATOR (A59823)
SANY SY225C 9C5KL...
2000 ITASCA SUNCRUISER 37G CLASS A RV (A58214)
2000 ITASCA...
2012 DOOSAN G25 GENERATOR (A58214)
2012 DOOSAN G25...
2009 MULTIQUIP 25KW GENERATOR (A55745)
2009 MULTIQUIP...
 
Top