buckeyefarmer
Epic Contributor
I had those type of wood trusses on my first house.
Curious as to the height of the wood joists vs. metal each spanning 24ft?
Might be cheaper but I doubt the same performance all things considered. I-shaped cross section is the most efficient way to design simple engineered beam where bending strength is driving factor vs. shear strength (web strength). The web does relatively little to help with bending strength. Trusses are another level of strength, where instead of relying on the web for stability and shear loads, the truss members are instead compression/tension members but they generally take more vertical space to be efficient... a la roof trusses.I bought direct from the factory. I was going to use a taller one, but they showed me a shorter one with a thicker web, that cost less and had same performance.
Locally those are known as tri-force joists. We looked at 3, LVL's, i-joists, and tri-force joists. LVL's were $250 each, 12" on center and can't drill. i-joists had issues with the span and were about $130 each and couldn't get wet, tri-force the guy at the supply yard recommended against them saying alot of people complain of sagging after a period of time.
The tradeready joists were $4024.83 for 33x 24' which was $121.96 each, $376.90 for the 5 at 14'10" which is $75.38, 9 pieces of rim track 12' 12ga for $515.31 or $57.26 each.
With the steel joists it feels like I'm getting the strongest product for the lowest cost. The rim track is extra though.
Locally those are known as tri-force joists. We looked at 3, LVL's, i-joists, and tri-force joists. LVL's were $250 each, 12" on center and can't drill. i-joists had issues with the span and were about $130 each and couldn't get wet, tri-force the guy at the supply yard recommended against them saying alot of people complain of sagging after a period of time.
The tradeready joists were $4024.83 for 33x 24' which was $121.96 each, $376.90 for the 5 at 14'10" which is $75.38, 9 pieces of rim track 12' 12ga for $515.31 or $57.26 each.
With the steel joists it feels like I'm getting the strongest product for the lowest cost. The rim track is extra though.
Are you going to have to use the self tapping screws from h*** for the sub floor?
I'm not sure what I'm doing for subfloor yet. The hex heads aren't going to work, I need a different self tapping screw which I don't have yet. I need to do bridging first though I think. Well, maybe not, if bridging pulls them out of 16" it would screw up my grid. It might be a good idea to put the plywood down first so I have everything in the correct position before I cut bridging.