I went ahead and put perforated drain pipe behind the block I have done so far.
I know, some think I’m nuts for doing the drain pipe when I haven’t even finished the first course yet, but I’ve had multiple cave-ins and I’m just trying to make sure I can get some wall up asap by the most susceptible area to cave.
I even have the apron area to pour yet. That’s the section with all the pieces of rebar.
 
   / AZ ranch #1,383  
I just now found my tool for smoothing the seam between blocks. I may not use it until the 5th course as everything below that will be covered in dirt, inside and out.
A small kitchen spoon works good as well.
You know you’ll misplace it again before course 5!!
 
   / AZ ranch
  • Thread Starter
#1,390  
About 12 block a day is what my back will tolerate. Then there’s tarring the outside and hauling/washing gravel for backfill, grinding and placing rebar, etc. The actual laying of block is about 25% of the job, so I’m happy with the progress rate.
 

Tractor & Equipment Auctions

TANK MANIFOLD (A55745)
TANK MANIFOLD (A55745)
ISUZU DUMP (A56858)
ISUZU DUMP (A56858)
2019 John Deere 85G Midi Excavator (A56857)
2019 John Deere...
LOT: Cutters, Shears, Giant Chalk Line, 100' Tape Measure (A59076)
LOT: Cutters...
2012 BMW 328i Sedan (A55758)
2012 BMW 328i...
LOT: Assortment of Opened Oil, Coolant, Parts Wash, Hydraulic Oil (A59076)
LOT: Assortment of...
 
Top