I went ahead and put perforated drain pipe behind the block I have done so far.
I know, some think I’m nuts for doing the drain pipe when I haven’t even finished the first course yet, but I’ve had multiple cave-ins and I’m just trying to make sure I can get some wall up asap by the most susceptible area to cave.
I even have the apron area to pour yet. That’s the section with all the pieces of rebar.
 
   / AZ ranch #1,383  
I just now found my tool for smoothing the seam between blocks. I may not use it until the 5th course as everything below that will be covered in dirt, inside and out.
A small kitchen spoon works good as well.
You know you’ll misplace it again before course 5!!
 
   / AZ ranch
  • Thread Starter
#1,390  
About 12 block a day is what my back will tolerate. Then there’s tarring the outside and hauling/washing gravel for backfill, grinding and placing rebar, etc. The actual laying of block is about 25% of the job, so I’m happy with the progress rate.
 

Tractor & Equipment Auctions

2015 Ford F550 Service Truck (A52377)
2015 Ford F550...
2018 VOLVO VNL DAY CAB (A52576)
2018 VOLVO VNL DAY...
2023 54ft Hooklift Dumpster 15 Cubic Yard (A55788)
2023 54ft Hooklift...
Ingersoll-Rand SD70 (A47477)
Ingersoll-Rand...
16' Driveway Gate (A53316)
16' Driveway Gate...
Honda Pioneer SXS700 4X4 Utility Cart (A55788)
Honda Pioneer...
 
Top