whitedogone
Gold Member
All this talk of POWER COMPANY OWNED EQUIPMENT. :laughing:
I work for a Utility Co. in NY, dealing with customers on this very issue. Try checking your Utilitiy's website for information on "service installations". Most have an online book for "General Specifications", which for my company, would answer almost all your questions listed here. If they don't, contact their New Business Dept., between that and the local electrical inspector, you'll have your answers. Be aware that every utility has their own set of rules, for instance, my Co. won't connect you if you used the 2.5" conduit, you would need 2" or 3" instead. But the next Company over insists on 2.5" conduit & won't allow 2" on their system. The Utility has the right, per NEC code, to demand things above & beyond the code books, so check with them before you buy anything.
If it were my decision, I would not install cable with inadequate insulation to be utilized in conduit with the size main breaker that you are using. So since you have said a 100 amp breaker will be installed, and that you have motor loads that can be considerable at start up (air compressor), I would buy cable that could handle the 100 amp load plus a small cushion. Looking at my calculator, that means #1 or 1/0 in aluminum with at least 75 degree centigrade insulation, (XHHW, THWN-2 or similar spec) for the current carrying legs. I suspect that it can be bought at the same price or maybe less than the direct burial cable and is better suited to this application.
You can read about cable size, insulation, etc. at Product Catalog in the aluminum building wire section.
So this would mean about 300 feet of this cable and 100 feet of #4 for the ground, assuming that the meter is at the pole. For single phase residential service, the ground bus is normally established at the meter box and disconnect.
All this talk of POWER COMPANY OWNED EQUIPMENT. :laughing:
They power company will not own the lines they will be customer owned by me. The own the main grid lines on the telephone pole but thats it. THey only thing they do is connect the line feeds to the meter socket and then connect my lines to the grid. Then they pop in a ringed meter and call it a day. I don't follow/understand what your statement means. Care to explain?
So, at what point does the power co. equipment end and your equipment end? If the power co had a pole set 1/2 mile down the road and I told them I was going to run underground from that point up the road to my meter base would that be fine with them? Would that 1/2 mile of underground be yours or theirs? It's the same thing you're saying. You must have a very strange power co if they allow you to run their laterals. I've never run into a poco anywhere in the country that would allow that.
They power company will not own the lines they will be customer owned by me. The own the main grid lines on the telephone pole but thats it. THey only thing they do is connect the line feeds to the meter socket and then connect my lines to the grid. THen they pop in a ringed meter and call it a day. I don't follow/understand what your statement means. Care to explain?
I'm not going to try and give you advice since I am not an electrician. However, I do have a few questions to clarify what you are talking about.
You mention a "pole", a "meter can/box", a "building/garage/shop" and a "breaker panel".
Is the meter on the pole or on the building? This makes quite a difference in what is needed on the pole. If the run is continuous from the weather-head, down the pole, into the ground and to a meter on the building, seems like only three wires would be needed at that point since the "ground" is picked up at the meter and the ground rod(s).
If the service runs from the weather-head to the meter on the pole and then to a breaker panel in the building, the top side of the meter from the weather-head to the meter would be three wires. There would be ground rod(s) at the base of the pole connecting to the meter according to your power company/county/city codes/requirements. Then 4 wires would run from the bottom of the meter to the breaker panel.
The "bonding" of the ground and neutral buses in the breaker panel and any additional ground rod(s) at the building would be according to your local codes/requirements.
At least that is the way it seems to me.
I do know that here, if you are the property owner and it is for "private use" (not commercial) you can pull the permit and do the wiring yourself - as long as it is done to code and passes inspection. This is not here-say or conjecture - I know because I have done my own wiring and it all passed inspection.