Detach 48x28 Garage - Footings

   / Detach 48x28 Garage - Footings #1  

Pettrix

Platinum Member
Joined
Jan 17, 2012
Messages
622
Location
High Desert Southwest
About to break ground on my 48x28 detached garage and on my engineering footing schedule it doesn't show any footings where the two 18' wide garage doors are. I know they are not "required" as there is nothing being supported wall wise there but someone told me that it's "better" to pour the footing under those doors as to keep the whole garage footing as a rectangle, making it stronger. One would run the horizontal footing bars but no vertical bars would be run since there is no wall being stacked on top of that area.

Is that true? Should I run a continuous footing underneath the garage doors or stop at the door area, and then restart again?

My engineering calls for a footing that is 18" below grade, 24" wide, 12" tall, with three #4 rebars at the bottom of the footing. Garage will be ICF (Insulated Concrete Forms) so I will be stacking ICF (6" concrete core) for the garage walls. I am using 4,500 psi concrete footing pour.
 
   / Detach 48x28 Garage - Footings #2  
That is correct. Pour a 12x12 footing under the doors and tie 1 or 2 rebar through so you have a complete loop around the perimeter for the strongest structure. ( Just my opinion from 45 yrs experience in this field)
 
   / Detach 48x28 Garage - Footings #3  
In reality the floor slab you pour will support the vehicle in/out traffic just fine, and the rest of the foundation will not somehow just come apart because it's not tied together in a full rectangle. Its a huge concrete footer, full of rebar, it'll be fine. The purpose is to support the vertical weight of the building - there shouldn't be pressure trying to explode the footer apart horizontally.

Your location of "desert" implies dry, stable soils and I presume you will be doing proper compaction of all soils underneath the footer and then also the interior floor slab.

But! I would do it also, if the cost of extra concrete doesn't ruin you. You only get one chance, don't skip anything that could lead to regrets.
 
   / Detach 48x28 Garage - Footings
  • Thread Starter
#4  
In reality the floor slab you pour will support the vehicle in/out traffic just fine, and the rest of the foundation will not somehow just come apart because it's not tied together in a full rectangle. Its a huge concrete footer, full of rebar, it'll be fine. The purpose is to support the vertical weight of the building - there shouldn't be pressure trying to explode the footer apart horizontally.

Your location of "desert" implies dry, stable soils and I presume you will be doing proper compaction of all soils underneath the footer and then also the interior floor slab.

But! I would do it also, if the cost of extra concrete doesn't ruin you. You only get one chance, don't skip anything that could lead to regrets.

Footings are poured on undisturbed native soil (once inspected by geo engineer). No fill or compaction is needed as long as the soil underneath the footing hasn't been disturbed after excavation. The interior slab (5") will have compacted 3/4"- AB (sand and 3/4" and smaller rock). Interior slab will be 5" thick, at a 4,500 psi mix, with #4 rebar at 24".
 
   / Detach 48x28 Garage - Footings #5  
I like having a footing under the opening. It supports the slab of concrete at the opening of the garage especially if heavy vehicles/equipment is entering there and keeps it from cracking or settling.
 
   / Detach 48x28 Garage - Footings #6  
In reality the floor slab you pour will support the vehicle in/out traffic just fine, and the rest of the foundation will not somehow just come apart because it's not tied together in a full rectangle. Its a huge concrete footer, full of rebar, it'll be fine. The purpose is to support the vertical weight of the building - there shouldn't be pressure trying to explode the footer apart horizontally.

Your location of "desert" implies dry, stable soils and I presume you will be doing proper compaction of all soils underneath the footer and then also the interior floor slab.

But! I would do it also, if the cost of extra concrete doesn't ruin you. You only get one chance, don't skip anything that could lead to regrets.
The SW deserts are on the San Andreas fault. There are literally hundreds of fault line fingers running off of the main fissure. The soil is mostly sand and rock. No doubt that added $150 cost to pour a bond beam accross the 2 doorways at the weakest point in the structure is a reasonable caution in my opinion based upon 35 yrs building experience in this SW desert area. I've lived through more big quakes here in the last 45 yrs than I can name including the 7.3 Landers quake.
 
   / Detach 48x28 Garage - Footings #7  
Good point, earthquakes are definitely not on our mind for building here in the midwest. Interesting that the engineer doing the plans found it unnecessary though.
 
   / Detach 48x28 Garage - Footings #8  
Good point, earthquakes are definitely not on our mind for building here in the midwest. Interesting that the engineer doing the plans found it unnecessary though.
😀 Two words: "New Madrid"

In addition to the size of the initial 1811 quake, there were reports of an earthquake every two hours for for five months.

I am not saying it should be top of mind for folks in the Midwest, but perhaps more top of mind than it is for most people. (tornados tend to be top of mind for me in the Midwest) I remember a small quake as a kid in the Midwest that jolted the house pretty good. The epicenter was over a hundred miles away.

FWIW: Earthquakes in the central part of the US tend to be felt at much larger distances. It is thought to be because many of them are caused by the North American plate cracking which then rings like a bell across the shield. The ringing tends to get buildings oscillating and that oscillation tends to increase the damage sustained for a given Richter level. That's one reason why buildings on fill do so poorly in earthquakes.

Did you know that Boston and San Francisco both have similar probabilities of Richter 7+ quakes in the next decade. Only one of them has seismic building codes...

Backto the OP's question
@Pettrix If you can afford it, I would definitely pour a footer across the door. It will be stronger, and will strengthen the floor, the driveway entrance ramp, and the integrity of the door.

All the best,

Peter
 
   / Detach 48x28 Garage - Footings #9  
Yeah I'm aware of the New Madrid fault but thats like 700 miles from Michigan (I should have said "upper" midwest I guess). We occasionally get mag 2-3 quakes here but I've never even noticed one while it's happening.

Pattrix, sounds like a robust building coming together. Can you share some pics as things progress?
 
   / Detach 48x28 Garage - Footings #10  
Have always done footers under the door. Even laid block under the door up to slab grade. We refer to that as a frost-wall. Laying block doesnt apply to you, as you are pouring walls.

Have you considered monolithic slab?
 
   / Detach 48x28 Garage - Footings
  • Thread Starter
#11  
Have always done footers under the door. Even laid block under the door up to slab grade. We refer to that as a frost-wall. Laying block doesnt apply to you, as you are pouring walls.

Have you considered monolithic slab?

We dug the footings as a complete rectangle so there will be a footing under the doors. We will run horiztonal rebar (three #4 bars in a 24" wide footing). We won't run any vertical bars under the door area but will of course have verticals at 32" and 16" oc depending on the wall area that was called out for.

I'm doing a 5" slab on grade pour after the ICF stem wall is done. Entire garage walls will be ICF (6" concrete core with 3" foam on each side).

All the footings and slabs will be 4,500 psi hydramix mix (water resistant). $168 per yard for that mix.
 
   / Detach 48x28 Garage - Footings #12  
just curious...will there be a concrete driveway poured up against the slab (depressed sill) ?
 
   / Detach 48x28 Garage - Footings
  • Thread Starter
#13  
just curious...will there be a concrete driveway poured up against the slab (depressed sill) ?

I believe so, will have to talk to contractor on how he will do that. More of a concrete apron that driveway. Less money as a driveway will cost me a lot of money.
 
   / Detach 48x28 Garage - Footings #14  
The SW deserts are on the San Andreas fault. There are literally hundreds of fault line fingers running off of the main fissure. The soil is mostly sand and rock. No doubt that added $150 cost to pour a bond beam accross the 2 doorways at the weakest point in the structure is a reasonable caution in my opinion based upon 35 yrs building experience in this SW desert area. I've lived through more big quakes here in the last 45 yrs than I can name including the 7.3 Landers quake.
I think you are referring to SW CA, but SW high deserts occur many places in the 4 corners states, and these are not earthquake prone regions.
 
   / Detach 48x28 Garage - Footings #15  
I poured footer and laid block up so the slab can sit on it. How much are you really saving by not doing it, on your $80,000 building? And if you don't, it's a hassle to work around. Are you also not going pour your footers on your man door?

It ties everything together, giving strength. It exists as one piece, the less seams the better.

nGaZOouh.jpg


3HUd4NNh.jpg


sM7KPCJh.jpg
 
   / Detach 48x28 Garage - Footings #16  
I typically build garages without a footer under the doors. Not so much for cost savings but it’s a lot easier to continue the construction process without a wall there. If the slab was going at ground level I’d probably go with a footer but when you’re filling the garage slab to above grade it doesn’t really help. When I pour the garage slap I pour it a little thicker with extra rebar in front of the doors. I’ve never had a problem doing that. Note I’m building residential garages that you couldn’t drive heavy equipment in if you wanted to. If I was planning on dump trucks going inside I might alter construction methods.
 
   / Detach 48x28 Garage - Footings #17  
I typically build garages without a footer under the doors. Not so much for cost savings but it’s a lot easier to continue the construction process without a wall there. If the slab was going at ground level I’d probably go with a footer but when you’re filling the garage slab to above grade it doesn’t really help. When I pour the garage slap I pour it a little thicker with extra rebar in front of the doors. I’ve never had a problem doing that. Note I’m building residential garages that you couldn’t drive heavy equipment in if you wanted to. If I was planning on dump trucks going inside I might alter construction methods.

Yeah that’s understandable. A lot of the old school guys did that, but then you only had 2-3 ton cars going in and out. I always view construction from a commercial or agricultural aspect and we always did a continuous wall with rebar. I think we even left out a course of block and poured the entrance part of the slab thicker- like 12” thick across the mouth of the opening for a few architects. Always was an ”overbuilder” and some of my subs hated me for it. lol

Here’s a 60’ x 30’ I built with 30” footings and 12” block below grade filled solid and vertical bar. Switched to 8” filled solid above grade

1673525716642.jpeg
 
Last edited:
   / Detach 48x28 Garage - Footings #18  
I believe so, will have to talk to contractor on how he will do that. More of a concrete apron that driveway. Less money as a driveway will cost me a lot of money.
Kust a suggestion...
With the slab poured first it can be advantageous to leave some rebar exposed where it can be used to tie the driveway to the foundation...can prevent separation...
 
   / Detach 48x28 Garage - Footings #19  
Yeah that’s understandable. A lot of the old school guys did that, but then you only had 2-3 ton cars going in and out. I always view construction from a commercial or agricultural aspect and we always did a continuous wall with rebar. I think we even left out a course of block and poured the entrance part of the slab thicker- like 12” thick across the mouth of the opening for a few architects. Always was an ”overbuilder” and some of my subs hated me for it. lol

Here’s a 60’ x 30’ I built with 30” footings and 12” block below grade filled solid and vertical bar. Switched to 8” filled solid above grade

View attachment 778899

If I was building an actual shop I’d build the floor sturdier but when I’m building a residential garage that’s only getting 8ft tall doors there’s zero possibility of dump trucks or something else heavy. I’ve set pallets in the garage with my skid steer though and I’ve never cracked a floor doing it.
 
   / Detach 48x28 Garage - Footings #20  
I think you are referring to SW CA, but SW high deserts occur many places in the 4 corners states, and these are not earthquake prone regions.
I suppose you are correct so long as you do not live in one of these areas (see US fault map)
US fault lines.jpg
 

Marketplace Items

2016 FORD TRANSIT T250 CARGO VAN (A59905)
2016 FORD TRANSIT...
JLG SKYTRACK 10054 TELESCOPIC FORKLIFT (A60429)
JLG SKYTRACK 10054...
(INOP) 2016 CATERPILLAR 259D SKID STEER (A60429)
(INOP) 2016...
Rhino DB150 (A57148)
Rhino DB150 (A57148)
KIVEL 48" PALLET FORKS 3500 LB CAP (A60430)
KIVEL 48" PALLET...
2020 PETERBILT 567 (A58214)
2020 PETERBILT 567...
 
Top