OP
tractchores
Veteran Member
I haven't posted on this in a while and thought I'd provide a quick update - especially if other folks think about similar projects. In the last few weeks there has been less digging and more loader work. My town uses the NEC rules for electrical code and for this job specifically table 300.5 governs the burial depth, conduit etc. The electrical inspector requires 3 different visits - Raw trench, trench with bedding and conduit and finally trench backfilled 12" with shading material and a warning ribbon run.
In my case I backfilled with around 10 yards of sand for the first run to create about 6" of bedding depth in the entire trench length. I then installed 3 conduit runs, 2 x 1" and 1 x 3/4". Code dictates that low voltage control wires (a phone cable and video cable in this case) be separate from the high voltage (120v) lines (2 in this case). The third is a spare. The conduit had to be schedule 40 PVC and in my case code required a cover depth of at least 12" (120v GFCI), but deeper is better. In my case the depth ranged from 30" to 18". As a trick to lay the conduit I built 20' sections in the garage and then covered the ends with socks and elastics to avoid getting a rock in it. We will pull 10 gauge wire for the electric to deal with voltage drop.
The conduit then needed to be shaded with 12" of sand (about 15 yards) and then marked with warning tape. Based on the huge number of rocks it was recommended that the trench be mostly back filled with sand to avoid issues, so another ~15 yards got it mostly filled. It's worth noting that the B2920 worked perfectly for the backfill, I was able to climb the spoils pile and get enough reach with the FEL to backfill over the pile VS trying to move it around or need access to both sides of the trench. I then pushed back the excavated soil into the trench minus rocks any bigger than about 6" across (per code). The interesting this was that even with the 40 yards of sand I still had low places because of the number of rocks I took out!
The next part of the project is the actual installation of the gate and low voltage control lines and a bore under the driveway to get power and control lines to the opposite side. Then everything can be wired up.
Here are some pictures of the trench work:

Conduit on sand bedding

Conduit on bedding, it curved nicely on the uphill portion and had more flex than I expected.

Shaded with 12" of sand and flagged with warning tape

In my case I backfilled with around 10 yards of sand for the first run to create about 6" of bedding depth in the entire trench length. I then installed 3 conduit runs, 2 x 1" and 1 x 3/4". Code dictates that low voltage control wires (a phone cable and video cable in this case) be separate from the high voltage (120v) lines (2 in this case). The third is a spare. The conduit had to be schedule 40 PVC and in my case code required a cover depth of at least 12" (120v GFCI), but deeper is better. In my case the depth ranged from 30" to 18". As a trick to lay the conduit I built 20' sections in the garage and then covered the ends with socks and elastics to avoid getting a rock in it. We will pull 10 gauge wire for the electric to deal with voltage drop.
The conduit then needed to be shaded with 12" of sand (about 15 yards) and then marked with warning tape. Based on the huge number of rocks it was recommended that the trench be mostly back filled with sand to avoid issues, so another ~15 yards got it mostly filled. It's worth noting that the B2920 worked perfectly for the backfill, I was able to climb the spoils pile and get enough reach with the FEL to backfill over the pile VS trying to move it around or need access to both sides of the trench. I then pushed back the excavated soil into the trench minus rocks any bigger than about 6" across (per code). The interesting this was that even with the 40 yards of sand I still had low places because of the number of rocks I took out!
The next part of the project is the actual installation of the gate and low voltage control lines and a bore under the driveway to get power and control lines to the opposite side. Then everything can be wired up.
Here are some pictures of the trench work:

Conduit on sand bedding

Conduit on bedding, it curved nicely on the uphill portion and had more flex than I expected.

Shaded with 12" of sand and flagged with warning tape
