The photos of the house aren't changing much lately as the pace of progress has slowed a bit. A lot has happened in the last couple of weeks though. We've got shingles on about half the roof, the basement and garage floors are poured and the chimney is going up.
This shot should prove interesting to the equipment junkies out there. The brick masons have a "hydro-platform" in use. It's like a self climbing tower crane on a slightly smaller scale. Built in hydraulics raise the platform and they put another set of leg extensions in then lower it onto the higher legs. Pretty slick set up. You can't tell in the photo but it says "15,000 pound max" on the side. Pretty amazing for a piece of equipment that folds down into it's own trailer pulled behind a pick-up truck. He's also got a telescoping forklift to move materials up to the platform.
In case you can't tell, I'm one of those equipment junkies /w3tcompact/icons/smile.gif