Jim: I agree, 1,000 cy is more than I dreamed we could move in a week but here are the numbers:
We ran 6 days at 10 hours per day, (60 hours total)
Average Cycles were 4.5 to 5 minutes per load
Average 1.5 cubic yards per load
60 hours x 60 minutes = 3,600 minutes
3,600 minutes / 5 minute cycles = 720 loads
720 loads x 1.5 cy per load = 1,080 cubic yards
We could have really improved our production if we had a place to dump that was closer. The one thing that helped our production was my Dad on the NH 8970 leveling and compacting the fill area at the dump site.
I really felt this was a good test to determine the capability of the scraper. I had quite a few spectators during the project (mostly farmers) who were amazed at the amount of dirt we could move an hour.